Fall Schedule Discussion
Jump to navigation
Jump to search
We need this information to present to Andrei as our plan for the remainder of FY21 and ask for his guidance going forward.
FY21 Schedule Discussion:
- Wastewater Irradiation Experiment Setup/Support (McCaughan) PPTX PDF
- Booster Assessment and Commissioning (Kazimi)
- Booster Removal & Relocation for Injector Phase 2 Upgrade (Poelker) poelker_mccaughan UITF plans for rest of 2021
- CIS Jobs for 2021-2022 (Grames) media:210623_CIS_UITF.docx media:210623_CIS_UITF.pdf
Please estimate the duration and resource (personnel, utility/cryogen, space) requirements for your tasks and experiments.