2022 Winter SAD ATLIS Tasks

Phase 1 Region

  • Install 200 kV w/o field emission
  • Replace DR dipole => PO for DR written week of Aug 30
  • Replace noisy Wien 20A SCE
  • Repair leaky PCUP LCW fitting
  • Remake A2 joint
  • Replace harp
  • Install & 200 kV kicker
Phase 2 Region
  • Possibly install solenoid/valve downstream of chopper
=> MMF making solenoid
=> valve in-hand ?
  • Requested to Steve brighter lights from laser room to gate (like we have by gun)

List of jobs https://wiki.jlab.org/ciswiki/index.php/Phase_2

CEBAF 200 kV Gun

  • Carlos - Status of small gun HV limits, CEBAF and UITF
  • Carlos - GTS gun HV design, i.e. reaching >200 kV w/o field emission
  • Gabriel - Picking the anode to eliminate kick
https://wiki.jlab.org/ciswiki/index.php/18%22_Photogun_ala_GTS