Announcements

  • Group and single photos next Wednesday
  • Tours for deputy of science David Dean, next Wed 3-5 @ 1137/UITF, and Fri 8-Noon @ GTS/LERF

Updates

  • CEBAF - media:220222_1330Report_Grames.pptx
  • UITF
    • Mar => Max's study of lifetime vs. gun voltage 100-200 kV
    • Apr => Install Wien & Mott, commission w/ beam
    • May => early install 200 KV gun if ready, or .... 2nd attempt at CsSbO activation => compare to life/pol vs. the Mar/Apr results
    • Jun => late install 200 KV gun at UITF, bake and HV condition
    • Jul => make beam 200 KV, FE zero?, lifetime bulk/780 ok?
    • Aug => latest to be ready to put beam into Booster, ready to commission Compton
    • Sep...Feb => group runs CEBAF, builds Phase2 @ TL, supports UITF as needed
    • Mar...Jun => install Phase2, commission beam, ready for CEBAF ops w/ 200 KV gun + booster
  • GTS

200 kV GUN

Standing Links