18" Photogun ala GTS
Jump to navigation
Jump to search
Timeline 2022
- April - finish design & assembly of Wien and Mott hardware, finish 200 KV HV vac work
- May - install Wien/Mott UITF, finish 200 KV gun assembly, restore polarized laser UITF
- June - install 200 keV gun, bake, big job, goal is making beam by ~July 4th weekend
- July - make 200 keV polarized beam, calibrate the Mott, using ~nA beam and U-Wien
- Aug - install Compton in MeV section, run keV beam as needed
- Sep/Oct - calibrate Compton, two separate ~week long runs