Goals/plans for beam test opportunity : Monday Feb 9 + Tuesday Feb 10

Tests that can happen at any energy
Test hardware TOF veto at 31MHz and 62MHz (6 hours)
Test FADC without TDC (2 hours)
Test background as a function of target ladder position on large target foil
Test FADC delayed operation (2 hours)
Tests that must happen at KE=5MeV
Measure emittance with Run 1 conditions (3 hours)
  • Note laser spot sizes have been reduced by about 2
  • Laser RF has been located closer to laser chassis
  • Laser chassis now has internal cooling