Development Period - February 9-10
Jump to navigation
Jump to search
Goals/plans for beam test opportunity : Monday Feb 9 + Tuesday Feb 10
Listed in order of suggested priority...
- Re-measure emittance in order to analyze Run 1 conditions (3 hours)
-
- Note laser spot sizes have been reduced by about 2
- Laser RF has been located closer to laser chassis
- Laser chassis now has internal cooling
- Test hardware TOF veto at 31MHz and 62MHz (6 hours)
- Test FADC without TDC (2 hours)
- Test background as a function of target ladder position on large target foil (2 hours)
- Test FADC delayed operation (2 hours)