Bubble Chamber Meeting Wednesday August 5, 2015
Jump to navigation
Jump to search
We will meet in TL 2221 on Wednesday August 5 at 3:30 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
1. Bubble Chamber progress at JLab
2. Laser Shuttering:
- Would like to use a mechanical shutter (100% extinction)
- John Hansknecht will build a control box that uses TLL signal on BNC cable (TTL=high=close=beam OFF, TLL=low=open=beam ON)
- LST400: on-hand, time to open (~30 ms), time to close (~30 ms), large aperture 8 mm
- LST202: purchase, time to open (~1.3 ms), time to close (~1.5 ms), small aperture 2.3 mm (recommend <1 mm beam)
- Alternatively use an electro-optic shutter (>1000:1 extinction, but fast rise/fall times <5 ns)
- repurposes cell in optical path, so more invasive and more work installing HV driver, control circuit)
3. Beam test of 5D line in the week of August 10 [2]
Notes from this meeting:
- Bubble Chamber:
- Chamber is in place
- Survey is scheduled on Friday
- Will do leak check, hydraulic check, chiller check and all other system checks including controlling the chamber from injector service building and MCC but will not turn chamber on
- TOSP Review is scheduled around August 18.
- Beam time is scheduled on Monday September 14 to Sunday September 20. Brad and Ernst will come few days earlier to turn chamber on.
- We need to come up with a run plan for September before the TOSP review.
- Laser Shutter:
- We decided on shutter LST400 with 30 ms open/close response time.
- Do we have the LabView TLL plug-in module?