September 30, 2015 - Fall Startup and Injector Tests
Jump to navigation
Jump to search
By Nov. 9th the following things MUST be accomplished.
1. CW beam to the inline dump 85uA from A laser, 1uA from the D laser
2. Wien setup for alignment of polarization to Hall-A on 5-pass
3. Quads, solenoids centered (where appropriate) and the determined BPMs SOF loaded, see item 6
4. Beam matched in the inj. chicane, ready for transport into the NL.
5. All lasers should produce beam with the same TWISS/emittance values as measured in the inj. chicane
6. RF calibration tool fully developed (anticipate Nov. 2-7 DAYS)
7. quad centering tool fully developed (anticipate Nov. 2-7 DAYS)
Injector Tests and Calendar media:150929_InjectorTestList.xlsx media:150929_InjectorTestList.pdf