Difference between revisions of "200 kV Polarized Gun"
Jump to navigation
Jump to search
(5 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
− | ==Meetings== | + | This area collects 200 kV installation at CEBAF. |
− | [[Feb 2, 2022 - Group meeting]] - Group meeting + 200 kV gun | + | |
− | [[200 kV Gun - Jan 26, 2022]] | + | == 200 kV Gun Installation Links == |
+ | * ATLIS => https://tasklists.jlab.org/atlis/tasks/108541 | ||
+ | * Marcy's Gantt chart goes here => | ||
+ | * List of photocathodes at end of Phase 1 (5/10/2021) - https://logbooks.jlab.org/entry/3876517 | ||
+ | |||
+ | ==Planning Meetings== | ||
+ | * Feb 20, 2023 => * Carlos SAD schedule [[Media:Gun swap planning 1 week before and 1 week after SAD start.pptx]] | ||
+ | * Feb 02, 2022 => [[Feb 2, 2022 - Group meeting]] - Group meeting + 200 kV gun | ||
+ | * Jan 26, 2022 => [[200 kV Gun - Jan 26, 2022]] | ||
== Links == | == Links == | ||
* [https://wiki.jlab.org/ciswiki/index.php/18%22_Photogun_ala_GTS Carlos 18" Gun Page] | * [https://wiki.jlab.org/ciswiki/index.php/18%22_Photogun_ala_GTS Carlos 18" Gun Page] | ||
* Gun Anode - Carlos's update https://wiki.jlab.org/ciswiki/index.php/Anode | * Gun Anode - Carlos's update https://wiki.jlab.org/ciswiki/index.php/Anode |
Revision as of 10:19, 10 March 2023
This area collects 200 kV installation at CEBAF.
200 kV Gun Installation Links
- ATLIS => https://tasklists.jlab.org/atlis/tasks/108541
- Marcy's Gantt chart goes here =>
- List of photocathodes at end of Phase 1 (5/10/2021) - https://logbooks.jlab.org/entry/3876517
Planning Meetings
- Feb 20, 2023 => * Carlos SAD schedule Media:Gun swap planning 1 week before and 1 week after SAD start.pptx
- Feb 02, 2022 => Feb 2, 2022 - Group meeting - Group meeting + 200 kV gun
- Jan 26, 2022 => 200 kV Gun - Jan 26, 2022
Links
- Carlos 18" Gun Page
- Gun Anode - Carlos's update https://wiki.jlab.org/ciswiki/index.php/Anode