2021-07-07
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- Supplementary Shielding Installation: ???
- Beamline Commissioning / Test Plans / Shielding Verification
- 7/26/21 Start Hot Check-out
- Commission new beam line and execute experiment
- Science!!!
New items for discussion:
Short term schedule update:
This week:
- Harp and NEG installed in MeV Spectrometer Line, [logbooks.jlab.org/entry/3883225 leak checked good].
- Corrector installation & cable reroute mostly complete, turned over to DC power
- BPM cabling rerouted & RF modules installed; turned over to IC/Software for integration
- Raster installation - completed; turned over to Bill Gunning
- Build 80/20 support structure for Pb (Completed)
- Pb stacked; some modification possibly required. RCG/ME discussing.
- Install target mechanism (Completed) - Survey required
- EES may start cabling downstream section & making UED updates.
- Ready to install Al base plates for FC3 region rework as well as solenoid stand. 80/20 reworked for support
- List of Engineering Jobs remaining
Gun work progressing well:
Still to do:
- Add Mu metal over bellows on wastewater line.
Next Week:
- Mount bottle rack in Labyrinth (Staged); remove gas bottles to rack.
- Unistrut mounting for cables - Neal will do when available
- Engineering work on beam line starting
2 weeks:
- Pull Heliax from Spectrum analyzer/Control room >> Buncher
- 4th terminal system in Control room under assembly/rebuild
- Items from To-do list...
Engineering Other business
Reports on Open Action Items:
Action Items:
- Formal run plan (McCaughan) Strawman