Difference between revisions of "April 7, 2017 - 200kV gun upgrade meeting"
Jump to navigation
Jump to search
(Created page with "== New action items == ===200kV Gun=== * Electrode submitted to shop * Shop finished bushing holder, in TL-1137 * Jay can help w/ 3D electrostatic model ===Gun2 NEG Tube===...") |
|||
(9 intermediate revisions by the same user not shown) | |||
Line 8: | Line 8: | ||
===Gun2 NEG Tube=== | ===Gun2 NEG Tube=== | ||
* Danny updated NEG tube | * Danny updated NEG tube | ||
+ | : [[media:NEGTUBE_MARCH31.pdf]] | ||
+ | : [[media:M20_BPM.pdf]] | ||
+ | : [[File:IMG_5188-1.JPG|200px]] | ||
+ | : [[File:IMG_5189-1.JPG|200px]] | ||
* John/Joe will decide on antenna plan next week | * John/Joe will decide on antenna plan next week | ||
Line 22: | Line 26: | ||
===SAD Schedule=== | ===SAD Schedule=== | ||
+ | * [https://accweb.acc.jlab.org/calendar/ SAD Calendar] | ||
+ | * Tasks [[media:170406_SAD_CIS.xlsx]] | ||
+ | * Pucks [[media:170407_SAD_Pucks.pptx]] |
Latest revision as of 10:54, 7 April 2017
New action items
200kV Gun
- Electrode submitted to shop
- Shop finished bushing holder, in TL-1137
- Jay can help w/ 3D electrostatic model
Gun2 NEG Tube
- Danny updated NEG tube
- John/Joe will decide on antenna plan next week
Gun3 Removal
- Matt check with Willeke next week during JLEIC meeting Gun3
- Maybe week May 8? to remove/replace Gun3 ATLIS task
Eliminating Gun Switch Software
- Kyle building a new screen, tracking to be ready in May or June