=== Accelerator Schedule===
 
 
* Physics run extended to May 6
 
 
* Completely new schedule: [[media:SAD-2018-SCHEDULE.xlsx]]
 
 
* Detailed Schedule (see page 2 for bubble): [[media:DoIt_rev1_180412.docx]] [[media:DoIt_rev1_180412.pdf]]
 
 
* Cryogenic plants are going to 4K on May 6
 
 
* Bubble will run at 4K - we will save time if we stay at 4K instead of waiting to go back to 2K (by Friday May 11th).
 
  
  
 
===Outside Visitors===
 
===Outside Visitors===
 
# Kevin (May 7 - 19)
 
# Thomas (May 7 - 14)
 
# Brad (May 7 - 18)
 
# David (May 10 - 19)
 
 
 
  - Tunnel Worker Safety Pre-brief (SAF132) walk-through part of the training is scheduled on May ? at ? (meet in MCC).
 
  
  
 
===Agenda===
 
===Agenda===
  
* New procedure for operations, '''''Argonne Bubble Chamber Operations for Engineering Runs''''': [[media:TGT-PROC-18-001.pdf]]
+
* Beam studies (4/24/18) - Alicia, Joe, Riad [[media:180426_beam_dryrun.docx]] [[media:180426_beam_dryrun.pdf]]  
 
 
 
 
* [[Accelerator Test Review]]
 
  
* Beam studies (4/24/18) - Alicia, Joe, Riad [[media:180426_beam_dryrun.docx]]  [[media:180426_beam_dryrun.pdf]]
 
  
 
* Installation Plan ([https://accweb.acc.jlab.org/calendar/ SAD Calendar)]
 
* Installation Plan ([https://accweb.acc.jlab.org/calendar/ SAD Calendar)]
Line 46: Line 20:
 
: Wed/9 - No lockups, S&A?
 
: Wed/9 - No lockups, S&A?
 
: Thu/10 - SWING lockup possible, anticipate 4K
 
: Thu/10 - SWING lockup possible, anticipate 4K
: Fri/11 - Anticipate 2K pumpdown and no lockup on DAY, 24/7 Ops support begins on SWING (w/ 2K or 4K until pumpdown read)
+
: Fri/11 - Anticipate 2K pumpdown and no lockup on DAY, 24/7 Ops support begins on SWING (w/ 2K or 4K until pumpdown ready)
  
* Bubble Chamber Run Plan
 
  
* '''Questions:'''
+
* New procedure for operations, '''''Argonne Bubble Chamber Operations for Engineering Runs''''': [[media:TGT-PROC-18-001.pdf]]
:: Does the Bubble Chamber equipment remain in the machine upon completion of the run this summer?
 
:: If yes, what special considerations will need to be taken to moth-ball the experiment?
 
  
  
* '''Open House:'''
+
* '''''5D line dump has been approved for 1 kW operation'''''
:: JLab Open House is on May 19, 2018 
 
:: Bubble Chamber display (Poster and Animation) is planned in MCC
 

Latest revision as of 11:46, 3 May 2018

We will meet in TL 2236 on Thursday April 26 at 4:00 pm EST.

For those calling in we'll use the Blue Jeans [1] audio conference system.

Phone number: 1-888-240-2560
Meeting ID: 3528502673#
Meeting URL: http://bluejeans.com/3528502673


Outside Visitors

Agenda


Mon/7 - No lockups, installation group, install harp + break
Tue/8 - No lockups, S&A?
Wed/9 - No lockups, S&A?
Thu/10 - SWING lockup possible, anticipate 4K
Fri/11 - Anticipate 2K pumpdown and no lockup on DAY, 24/7 Ops support begins on SWING (w/ 2K or 4K until pumpdown ready)



  • 5D line dump has been approved for 1 kW operation