Line 39: | Line 39: | ||
* '''''Bubble Installation:''''' March 26 - April 6, 2018 | * '''''Bubble Installation:''''' March 26 - April 6, 2018 | ||
:: Installation on DAY shift, early lock-up about 3 pm for PSS certification | :: Installation on DAY shift, early lock-up about 3 pm for PSS certification | ||
− | :: Support needed: installation, alignment, source, networking, computing | + | :: Support needed: installation, alignment, source, networking, computing |
− | * '''''Bubble Run I:''''' April | + | * '''''Bubble Run I:''''' April 23 - May 6, 2018 |
− | :: | + | :: Day: Beam Setup |
− | :: | + | :: Swing - Owl: Data taking |
− | :: | + | :: 2K |
− | * '''''Bubble Run II:''''' August 6 - August | + | * '''''Bubble Run II:''''' August 6 - August 19, 2018 |
Revision as of 13:55, 6 February 2018
We will meet in TL 2236 on Thursday February 8 at 4:00 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Moderator Passcode: 5978# Meeting URL: http://bluejeans.com/3528502673
Agenda
- Bubble Chamber work at ANL
- Neutron count rate made with single fluid chamber over a period of 1.5 months: media:Bubble_neutronrate_Feb2018.pdf
- Whitney Armstrong - Geant4 Simulation
- Claudio Ugalde - Software development
- Seamus Riordan - 19F(γ,α)15N Run Plan
- Bubble Chamber Beam Requirements
- Questions:
- Can we run the chamber from MCC instead of Injector Service Building?
- Is it possible to save a unique identification tag of each bubble event in EPICS Archiver?
Accelerator Schedule
- Bubble Installation: March 26 - April 6, 2018
- Installation on DAY shift, early lock-up about 3 pm for PSS certification
- Support needed: installation, alignment, source, networking, computing
- Bubble Run I: April 23 - May 6, 2018
- Day: Beam Setup
- Swing - Owl: Data taking
- 2K
- Bubble Run II: August 6 - August 19, 2018