Line 27: Line 27:
  
  
* Beam Schedule in 2016:
+
* Schedule in 2016:
# Test Run II: May 30 – June 20
+
# Beam Test Run II: May 30 – June 20
# Test Run III: Aug 15 – Aug 29
+
# Beam Test Run III: Aug 15 – Aug 29
 
# Installation of chamber in Injector can be in:
 
# Installation of chamber in Injector can be in:
 
## April 14 – April 30, 2016 (while accelerator scheduled for ''Cryo Configuration Change''), or
 
## April 14 – April 30, 2016 (while accelerator scheduled for ''Cryo Configuration Change''), or
Line 36: Line 36:
 
## Winter Shutdown (Jan 4 – Jan 27), or
 
## Winter Shutdown (Jan 4 – Jan 27), or
 
## April 14 – April 30, 2016
 
## April 14 – April 30, 2016
 +
 +
* Brad is preparing to change chamber to single fluid with new cooling system.
 +
# Do we want to change to a collimator inside chamber? made of silver instead of copper?
 +
# Do we want to use hydraulic oil with higher content of hydrogen to help moderate neutrons?
 +
 +
* Recent data analysis results:
 +
#

Revision as of 10:02, 10 December 2015

We will meet in TL 2221 on Wednesday December 9 at 3:30 pm EST.

For those calling in we'll use the Blue Jeans [1] audio conference system.

Phone number: 1-888-240-2560
Meeting ID: 3528502673#
Meeting URL: http://bluejeans.com/3528502673


Agenda:

1- Experiment Schedule (listed as Injector Facility Development Time): [2]

2- Bubble Chamber work at ANL

3- Sept beam test data analysis: media:Rate_N2O.pdf media:Rate_N2O.pptx

4- Discussion of June 2016 beam test: media:sigma_f19ga_low.pdf

5- Summary of Sept Beam Test: media:BeamTest_Summary_II_Sept2015.pdf media:BeamTest_Summary_II_Sept2015.pptx




Notes from this meeting:


  • Schedule in 2016:
  1. Beam Test Run II: May 30 – June 20
  2. Beam Test Run III: Aug 15 – Aug 29
  3. Installation of chamber in Injector can be in:
    1. April 14 – April 30, 2016 (while accelerator scheduled for Cryo Configuration Change), or
    2. During first week of Run II.
  4. Modification to beamline can be during:
    1. Winter Shutdown (Jan 4 – Jan 27), or
    2. April 14 – April 30, 2016
  • Brad is preparing to change chamber to single fluid with new cooling system.
  1. Do we want to change to a collimator inside chamber? made of silver instead of copper?
  2. Do we want to use hydraulic oil with higher content of hydrogen to help moderate neutrons?
  • Recent data analysis results: