Difference between revisions of "Bubble Chamber Readiness Review Meeting: Thursday September 11, 2014"
Jump to navigation
Jump to search
(2 intermediate revisions by the same user not shown) | |||
Line 14: | Line 14: | ||
* Preliminary schedule of the review process: | * Preliminary schedule of the review process: | ||
# Bubble Chamber Safety Review: First week of December 2014 - to be able to bring the chamber on site and test it with a source. | # Bubble Chamber Safety Review: First week of December 2014 - to be able to bring the chamber on site and test it with a source. | ||
− | # Experiment Readiness Review (Preliminary): First week of January 2015 - to be able to install the chamber in the injector and | + | # Experiment Readiness Review (Preliminary): First week of January 2015 - to be able to install the chamber in the injector and do beam studies with the test beamline and chamber. |
− | # Experiment Readiness Review: First week of May 2015 - to be able to schedule (ask for PAC days) and run the experiment at the end of Summer 2015. | + | # Experiment Readiness Review: First week of May 2015 - to be able to schedule (ask for PAC days), commission and run the experiment at the end of Summer 2015. |
Latest revision as of 17:50, 22 September 2014
Agenda:
1- Start the Readiness Review process: media:Bubble_Chamber_Readiness_11Sept2014.pdf media:Bubble_Chamber_Readiness_11Sept2014.pptx
Notes from this meeting:
- Attendees: Rossi, Freyberger, Poelker, Meekins, Grames, and Suleiman.
- Preliminary schedule of the review process:
- Bubble Chamber Safety Review: First week of December 2014 - to be able to bring the chamber on site and test it with a source.
- Experiment Readiness Review (Preliminary): First week of January 2015 - to be able to install the chamber in the injector and do beam studies with the test beamline and chamber.
- Experiment Readiness Review: First week of May 2015 - to be able to schedule (ask for PAC days), commission and run the experiment at the end of Summer 2015.