Development Period - February 9-10

From Ciswikidb
Revision as of 15:35, 9 February 2015 by Suleiman (talk | contribs)
Jump to navigation Jump to search

Listed in order of suggested priority...

  1. Re-measure emittance in order to analyze Run 1 conditions (3 hours)
  2. Test hardware TOF veto at 31MHz and 62MHz (6 hours)
  3. Test FADC without TDC (1 hour). February 4, 2015: Added two more laser timing signals to FADC. From Disc 708, OUT signal was connected to FADC Ch10 and OUT_bar was connected to Ch12. The original laser timing signal is still connected to Ch9.
  4. Test background as a function of target ladder position on large target foil (2 hours)
  5. Test Mott delayed operation (1 hour): a set of 10 runs while changing between No Delay and Delay=8.
  6. Test new Mott DAQ Configurations (1 hour): SemiIntFast (only readout of fADC250. Blocklevel = 1) and SemiIntBlock (only readout of fADC250. Blocklevel = 50)