Difference between revisions of "Feb 2, 2022 - Group meeting"

From Ciswikidb
Jump to navigation Jump to search
Line 8: Line 8:
  
 
==CEBAF SAD [[Schedule Accelerator Down]]==
 
==CEBAF SAD [[Schedule Accelerator Down]]==
* Next two weeks
+
* Next two weeks  
 
** Feb 8-10 - install ML fiber laser, lock up Feb 11 for HCO (https://opsweb.acc.jlab.org/CSUEApps/atlis/task/22830)
 
** Feb 8-10 - install ML fiber laser, lock up Feb 11 for HCO (https://opsweb.acc.jlab.org/CSUEApps/atlis/task/22830)
** Feb 14-20 - 12 shifts for beam studies
+
** Feb 14-20 - 12 shifts for beam studies - (Daniel will organize meeting Tue Feb 8 in afternoon to discuss beam studies)
*** Characterize ML laser (pulse length, bleed through, high current setup to fc#2) - (https://opsweb.acc.jlab.org/CSUEApps/atlis/task/22830)
+
*** Joe - Characterize ML laser (pulse length, bleed through, high current setup to fc#2) - (https://opsweb.acc.jlab.org/CSUEApps/atlis/task/22830)
*** Characterize noise on Wien magnets 10 A trims vs. 20 A SCE (https://opsweb.acc.jlab.org/CSUEApps/atlis/task/23781)
+
*** Riad - Characterize noise on Wien magnets 10 A trims vs. 20 A SCE (https://opsweb.acc.jlab.org/CSUEApps/atlis/task/23781)
*** Characterize gun kick vs. laser position and gun voltage? (NEEDS ATLIS)
+
*** Max - Characterize gun kick vs. laser position and gun voltage? (NEEDS ATLIS)
 
* Feb 21 - Apr 28
 
* Feb 21 - Apr 28
 
** CIS - Decide if ML laser remains for next run, or backout to GS
 
** CIS - Decide if ML laser remains for next run, or backout to GS

Revision as of 10:32, 2 February 2022

Meeting Coordinates

Announcements

  • CIS job vacancies
  • Hybrid work policy

CEBAF SAD Schedule Accelerator Down

Updates from GTS & UITF

  • GTS
  • UITF
    • Feb - SAD + Lifetime vs. Gun voltage (Max)
    • Mar - Wrap up BS + Wien/Mott vacuum work
    • Apr - Wrap up vacuum work + CsSbO2 lifetime (Mamun/Max)
    • May - Wrap up lifetime + install 200 kV gun
    • Jun - Wrap up gun install + commission gun 200 - 3?? kV

200 kV GUN

Standing Links