GTS meeting 11 15 16
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
- Bunch charge versus frequency for different average beam currents:
- Laser power needed to generate each beam current (at 532 nm and with QE=1%):
- The gun bake is complete (less than 10% in pressure over 24 hours)
- We wil activate the NEGs, followed by cool down Wednesday morning
- Thursday we will clean up and setup for high voltage ops
- Target day for starting HV conditioning is this Friday Nov 18
- GTS PSS certification complete, except for the laser part
- The slits are being assembled in TL1137 clean room, but there seems to be material only for horizontal slits.
- Media:haysg_JL0035130-EMS SLIT SYSTEM ASSEMBLY.pdf