(Created page with "* File:Fay's 3D sims R30+Yan's shed.pdf * The cathode prep chamber is coming together albeit at much slower pace than anticipated, lots of fixes on-the-go. **Phil has ass...")
 
Line 1: Line 1:
* [[File:Fay's 3D sims R30+Yan's shed.pdf]]
+
* [[Media:Fay's 3D sims R30+Yan's shed.pdf]]
  
 
* The cathode prep chamber is coming together albeit at much slower pace than anticipated, lots of fixes on-the-go.
 
* The cathode prep chamber is coming together albeit at much slower pace than anticipated, lots of fixes on-the-go.

Revision as of 12:57, 22 February 2016

  • The cathode prep chamber is coming together albeit at much slower pace than anticipated, lots of fixes on-the-go.
    • Phil has assembled the top flange with two NEG WPs, a viewport, the mask (on a translation stage), and the anode collector ring.
    • The two garage manipulators are installed, as is the Cs-K effusion source. Mamun loaded the K and Cs ampules.
    • The Sb boat manipulator is installed but needs to be loaded by Mamun.
    • The bottom heater is installed, it might need a longer lead screw.
    • The ion pump was relocated to the back of the chamber below the long puck manipulator.
    • The RGS needs to be installed, we'll do this last.
    • Still needed: Heater controls for each of the two cathode heaters and for the effusion sources. Motor and controls for moving up and down the bottom heater. Power supply for the Sb boat.