January 13, 2020 - Service providers

From Ciswikidb
Revision as of 10:27, 13 January 2020 by Grames (talk | contribs) (Created page with "Service providers discussion ===Scope of 2020 SAD=== * Booster will remain at UITF in 2020 to commission HDIce, nominally moves to CEBAF in 2021 during summer SAD. * During t...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Service providers discussion

Scope of 2020 SAD

  • Booster will remain at UITF in 2020 to commission HDIce, nominally moves to CEBAF in 2021 during summer SAD.
  • During the 2020 SAD we will...
Make the gun operate a 200 kV
Reconfigure beam line extending from gun through chopper
Commission the new gun and beam line with 200 keV beam

Beyond 2020 SAD

  • We will not modify the configuration downstream of chopper until new Booster goes in
This means the capture and QCM remain until Booster installed
This also means we'll operate the gun and beam line at 130 keV until that time too