Let's meet and discuss progress of upgrade on Wednesday, July 13 @ 10am in TL-1227.
Laser Installation
- Laser table rebuild
- Communications to IPG/PPLN
- Remaining tasks
Hardware Controls
- Macropulse chassis installation
- SCAM board, firmware, ioc software
- HCO
PSS
- PSS Upgrade for HVPS
- PSS laser shutters
- PSS certification
Software Controls
- Add 4th laser to applications
- Add 4th laser to screens