Line 7: | Line 7: | ||
* Communications to IPG/PPLN | * Communications to IPG/PPLN | ||
* Remaining tasks | * Remaining tasks | ||
− | * PGun Ops Screengrab [[File:160713_4laser.jpeg | + | * PGun Ops Screengrab [[File:160713_4laser.jpeg]] |
=== Hardware Controls === | === Hardware Controls === |
Revision as of 09:34, 13 July 2016
Let's meet and discuss progress of upgrade on Wednesday, July 13 @ 10am in TL-1227.
Laser Installation
Hardware Controls
- Macropulse chassis installation
- SCAM board, firmware, ioc software
- HCO
PSS
- PSS Upgrade for HVPS
- PSS laser shutters
- PSS certification
Software Controls
- Add 4th laser to applications
- Add 4th laser to screens