Difference between revisions of "July 13, 2016 - Monthly 4-laser Upgrade Status Meeting"

From Ciswikidb
Jump to navigation Jump to search
 
(13 intermediate revisions by the same user not shown)
Line 1: Line 1:
Let's meet and discuss progress of upgrade on Wednesday, July 13 @ 11am in TL-1227.
+
Let's meet and discuss progress of upgrade on Wednesday, July 13 @ 10am in TL-1227.
 +
 
 +
[[File:4-laser-olympics.png|center|300px]]
  
 
=== Laser Installation ===
 
=== Laser Installation ===
** Laser table rebuild
+
* Laser table rebuild [[File:160713_4layout.png|100px]]
** Communications to IPG/PPLN
+
* Communications to IPG/PPLN
** Remaining tasks
+
* Remaining tasks
 +
* PGun Ops Screengrab [[File:160713_4laser.jpeg|100px]]
  
=== Controls ===
+
=== Hardware Controls ===
** Macropulse chassis
+
* Macropulse chassis installation
** SCAM
+
* SCAM board, firmware, ioc software
 +
* HCO
  
 
=== PSS ===
 
=== PSS ===
** [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/16382 PSS Upgrade for HVPS]
+
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/16382 PSS Upgrade for HVPS]
** PSS laser shutters
+
* PSS laser shutters
** PSS certification
+
* PSS certification
 +
 
 +
=== Software Controls ===
 +
* Add 4th laser to applications
 +
* Add 4th laser to screens
  
 
=== Commissioning ===
 
=== Commissioning ===
 +
* [[media:160712_4laser_commission.docx]]

Latest revision as of 09:44, 13 July 2016

Let's meet and discuss progress of upgrade on Wednesday, July 13 @ 10am in TL-1227.

4-laser-olympics.png

Laser Installation

  • Laser table rebuild 160713 4layout.png
  • Communications to IPG/PPLN
  • Remaining tasks
  • PGun Ops Screengrab 160713 4laser.jpeg

Hardware Controls

  • Macropulse chassis installation
  • SCAM board, firmware, ioc software
  • HCO

PSS

Software Controls

  • Add 4th laser to applications
  • Add 4th laser to screens

Commissioning