March 1, 2021 - DC/Magnet Installation Kickoff
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Meeting Info =
We will meet Monday March 1 following Steve's 1:30 pm via BlueJeans:
We will gather Monday at 1330 to continue the SAD discussion. https://bluejeans.com/569476853
Agenda
- Installation status
- Schedule
- Transition from vac/mech to girder hook-ups planned to begin April 5 (5 weeks from today)
- We may be ready early by 1 or 2 weeks (no sooner than mid-March)
- Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30) w/ HCO/System readiness for everything up to FC#2
- Preliminary Songsheet
- Updated as of Feb 23 on the upgrade home page => CEBAF Injector Upgrade
- What to expect in tunnel?
- Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2)
- There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory
- Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable trays (above & on girder) + 3 cable bundle drops (Y, Laser, Chopper)
- DC/Magnet Jobs
- Spreadsheet with magnet information updated as of Mar 1 media:210301_Phase1_Magnet_Summary.xlsx
- Software Jobs
- CED
- Apps
- Screens
- What else for software?
- Other magnet jobs
- (JM) Complete magnet table I circulated
- (JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
- (RS/GC) FG solenoid special hysteresis for Gary
- (RS/MJ) Magnet info for Inj Steer spin calculations
- (JM/JG) Decision on spare DR fabrication and alignment
- (LL/JK/JM) PSS kicker - does MMF have any responsibility here, maybe just PSS?
- (LL/JM) Second QW measurement, what's the scope here?
- (JM) When is the rotating coil stand ready?
- (JM/LL) Reconciling MHD discrepancy
- (LL) Report on QW
- (LL) Report on HD
- (LL) Report on PSS kicker
- CIS Magnet Jobs
- Plans
- Jobs list => Phase 1 area on the upgrade home page => CEBAF Injector Upgrade
- Meet in 2 weeks?