== Summary == | == Summary == | ||
− | + | ;4-LLRF Installation | |
− | Prototype 4-LLRF on track for SAD, requires about one week for install and RF testing [[media::4Laser_LLRF_March_ready.ppt]] | + | * Prototype 4-LLRF on track for SAD, requires about one week for install and RF testing [[media::4Laser_LLRF_March_ready.ppt]] |
− | FSD interface will monitor 35/70 MHz signals, thresholds set in EPICS, Rama will work w/ Brad to connect to FSD system | + | * FSD interface will monitor 35/70 MHz signals, thresholds set in EPICS, Rama will work w/ Brad to connect to FSD system |
− | As known, system will not detect 499MHz flip, requires upgrade of MO distribution for 250MHz | + | * As known, system will not detect 499MHz flip, requires upgrade of MO distribution for 250MHz |
− | Rama/Scott/Clyde will meet before/during | + | * Rama/Scott/Clyde will meet before/during |
− | Present laser RF remains in rack, new 4-LLRF installed by buncher/chopper RF, 4-LLRF application recycles existing RF channel names | + | * Present laser RF remains in rack, new 4-LLRF installed by buncher/chopper RF, 4-LLRF application recycles existing RF channel names |
− | Michele's HLAPP test will happen once manual control tested okay | + | * Michele's HLAPP test will happen once manual control tested okay |
− | Bench test isolation between RF channels >45 dB | + | * Bench test isolation between RF channels >45 dB |
− | Tomasz wants to know how precisely power level set for 10 dBm | + | * Tomasz wants to know how precisely power level set for 10 dBm |
− | + | ;4-Beam Testing |
Revision as of 13:00, 13 March 2017
Let's meet Monday March 13th at 11am in the MCC conference room to organize 4-LLRF installation and commissioning. Please come prepared to speak to relevant items below, and/or invite those whom should attend. We'll end the meeting with a ~firm plan that Steve can post to the SAD calendar.
Topics
- Plan for 4-LLRF installation
- Software controls and screen readiness
- FSD implementation and testing
- First connection to lasers, manual testing 249/499
- Remote HLLAP control of laser frequency
- Repair bunch length
- Schedule for beam operations
- Beam tests: chopper, bunch length, energy spread
- Dry run for Fall 4-beam ops
- Running during the summer
- Installation of final system
- Any other topic you'd like to discuss
Summary
- 4-LLRF Installation
* Prototype 4-LLRF on track for SAD, requires about one week for install and RF testing [[media::4Laser_LLRF_March_ready.ppt]] * FSD interface will monitor 35/70 MHz signals, thresholds set in EPICS, Rama will work w/ Brad to connect to FSD system * As known, system will not detect 499MHz flip, requires upgrade of MO distribution for 250MHz * Rama/Scott/Clyde will meet before/during * Present laser RF remains in rack, new 4-LLRF installed by buncher/chopper RF, 4-LLRF application recycles existing RF channel names * Michele's HLAPP test will happen once manual control tested okay * Bench test isolation between RF channels >45 dB * Tomasz wants to know how precisely power level set for 10 dBm
- 4-Beam Testing