Let's meet Monday March 13th at 11am in the MCC conference room to organize 4-LLRF installation and commissioning. Please come prepared to speak to relevant items below, and/or invite those whom should attend. We'll end the meeting with a ~firm plan that Steve can post to the SAD calendar.

1. Plan for 4-LLRF installation 2. Software controls and screen readiness 3. FSD implementation and testing 4. First connection to lasers, manual testing 249/499 5. Remote HLLAP control of laser frequency 6. Repair bunch length 7. Schedule for beam operations 8. Beam tests: chopper, bunch length, energy spread 9. Dry run for Fall 4-beam ops 10. Running during the summer 11. Installation of final system 12. Any other topic you'd like to discuss