(Created page with "We'll meet on Wednesday March 9 in TL-1227 for around-the-table updates preparing for the summer SAD 4-laser upgrade. The agenda below is meant to explore the different acti...") |
|||
(8 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
We'll meet on Wednesday March 9 in TL-1227 for around-the-table updates preparing for the summer SAD 4-laser upgrade. The agenda below is meant to explore the different activities, please add/edit as makes sense, post material to share or send me in advance and I can add it. | We'll meet on Wednesday March 9 in TL-1227 for around-the-table updates preparing for the summer SAD 4-laser upgrade. The agenda below is meant to explore the different activities, please add/edit as makes sense, post material to share or send me in advance and I can add it. | ||
− | == | + | === Schedule (Joe) === |
+ | Discuss modified Summer SAD schedule, remind people of constraints | ||
+ | * The project has shifted the Hall-B run by two weeks. | ||
+ | * [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/SSAD2016.html Summer SAD] | ||
− | === | + | === Laser Status (John) === |
− | + | * Status for 4th laser amplifier, components to complete 4th laser + additional optical path | |
− | + | * New RTP scheme | |
+ | * New PSS shutter complete? | ||
+ | * Timeline | ||
− | == SCAM-II == | + | === SCAM-II (Roger) === |
+ | * Status for SCAM-II development | ||
+ | * Comment on additional requests for aux trigger (Jordan) and Mizar functions (Tiefenback) | ||
+ | * When do you want requirements document for SCAM-II finalized, already? | ||
+ | * Software integration | ||
+ | * Timeline | ||
− | == LLRF == | + | === LLRF (Tomasz) === |
+ | Status, plans and time line of LLRF sub-systems [[media:160409_LLRF.ppt]] | ||
+ | * Front end LO | ||
+ | * LCLS-II digitizer | ||
+ | * LCLS or Commercial FPGA or PC104 | ||
+ | * Software integration | ||
+ | * Timeline |
Latest revision as of 10:55, 9 March 2016
We'll meet on Wednesday March 9 in TL-1227 for around-the-table updates preparing for the summer SAD 4-laser upgrade. The agenda below is meant to explore the different activities, please add/edit as makes sense, post material to share or send me in advance and I can add it.
Schedule (Joe)
Discuss modified Summer SAD schedule, remind people of constraints * The project has shifted the Hall-B run by two weeks. * Summer SAD
Laser Status (John)
* Status for 4th laser amplifier, components to complete 4th laser + additional optical path * New RTP scheme * New PSS shutter complete? * Timeline
SCAM-II (Roger)
* Status for SCAM-II development * Comment on additional requests for aux trigger (Jordan) and Mizar functions (Tiefenback) * When do you want requirements document for SCAM-II finalized, already? * Software integration * Timeline
LLRF (Tomasz)
Status, plans and time line of LLRF sub-systems media:160409_LLRF.ppt * Front end LO * LCLS-II digitizer * LCLS or Commercial FPGA or PC104 * Software integration * Timeline