We'll meet on Wednesday March 9 in TL-1227 for around-the-table updates preparing for the summer SAD 4-laser upgrade. The agenda below is meant to explore the different activities, please add/edit as makes sense, post material to share or send me in advance and I can add it. | We'll meet on Wednesday March 9 in TL-1227 for around-the-table updates preparing for the summer SAD 4-laser upgrade. The agenda below is meant to explore the different activities, please add/edit as makes sense, post material to share or send me in advance and I can add it. | ||
− | |||
− | |||
=== Schedule (Joe) === | === Schedule (Joe) === | ||
Line 20: | Line 18: | ||
=== LLRF (Tomasz) === | === LLRF (Tomasz) === | ||
− | Status and | + | Status, plans and time line of new LLRF sub-systems... |
− | + | * Front end LO | |
− | + | * LCLS-II digitizer | |
− | + | * LCLS or Commercial FPGA or PC104 | |
− | + | * Software integration plan | |
− | + | * Timeline | |
− | |||
− | * | ||
− | * | ||
− | |||
− | * | ||
− | |||
− | |||
− | |||
− |
Revision as of 11:16, 4 March 2016
We'll meet on Wednesday March 9 in TL-1227 for around-the-table updates preparing for the summer SAD 4-laser upgrade. The agenda below is meant to explore the different activities, please add/edit as makes sense, post material to share or send me in advance and I can add it.
Schedule (Joe)
Discuss modified Summer SAD schedule, remind people of constraints
Laser Status (John)
Status for 4th laser amplifier, components to complete 4th laser + additional optical path New RTP scheme New PSS shutter complete? What else?
SCAM-II (Roger)
Status for SCAM-II development Comment on additional requests / timeline: 1. Kevin Jordan provide requirements for an auxiliary beam sync trigger, 2. Michael Tiefenback say whether to retain Mizar board, or what Mizar-like functions desired When do you want requirements document for SCAM-II finalized, already?
LLRF (Tomasz)
Status, plans and time line of new LLRF sub-systems... * Front end LO * LCLS-II digitizer * LCLS or Commercial FPGA or PC104 * Software integration plan * Timeline