Line 11: | Line 11: | ||
;Phase 2 Region | ;Phase 2 Region | ||
− | * Possibly install solenoid/valve downstream of chopper | + | * Possibly install solenoid/valve downstream of chopper => MMF mapping solenoids in Sep. Do we have 2-3/4" pneumatic beam line valve? |
− | + | * Install bright lighting => Walked area with FM. Waiting for follow-up. | |
− | |||
− | * | ||
− | |||
− | |||
===CEBAF 200 kV Gun=== | ===CEBAF 200 kV Gun=== |
Revision as of 08:55, 7 September 2021
2022 Winter SAD ATLIS Tasks
Phase 1 Region
- Install 200 kV w/o field emission
- Replace DR dipole => PO for DR written week of Aug 30
- Replace noisy Wien 20A SCE
- Repair leaky PCUP LCW fitting
- Remake A2 joint
- Replace harp
- Install & 200 kV kicker
- Phase 2 Region
- Possibly install solenoid/valve downstream of chopper => MMF mapping solenoids in Sep. Do we have 2-3/4" pneumatic beam line valve?
- Install bright lighting => Walked area with FM. Waiting for follow-up.
CEBAF 200 kV Gun
- Carlos - Status of small gun HV limits, CEBAF and UITF
- Carlos - GTS gun HV design, i.e. reaching >200 kV w/o field emission
- Gabriel - Picking the anode to eliminate kick