- 18:16, 27 October 2020 diff hist +14 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 18:15, 27 October 2020 diff hist +27 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 18:14, 27 October 2020 diff hist +2 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 18:12, 27 October 2020 diff hist +153 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 18:08, 27 October 2020 diff hist +283 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:24, 27 October 2020 diff hist +68 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:07, 27 October 2020 diff hist +40 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:05, 27 October 2020 diff hist +57 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 08:27, 27 October 2020 diff hist +222 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 21:42, 26 October 2020 diff hist 0 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 21:41, 26 October 2020 diff hist 0 N File:InjSB Week6.png current
- 21:24, 26 October 2020 diff hist +22 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 21:21, 26 October 2020 diff hist +188 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 13:12, 26 October 2020 diff hist +84 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:40, 26 October 2020 diff hist +3 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 16:22, 23 October 2020 diff hist 0 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 16:22, 23 October 2020 diff hist 0 CIS Phase 1 work plans
- 16:20, 23 October 2020 diff hist -4 CIS Phase 1 work plans
- 16:18, 23 October 2020 diff hist +104 CIS Phase 1 work plans
- 16:12, 23 October 2020 diff hist -140 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 14:56, 23 October 2020 diff hist +115 CEBAF Injector Upgrade →ATLIS Tasks
- 14:25, 23 October 2020 diff hist -3 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 12:01, 23 October 2020 diff hist -8 Useful Links
- 09:42, 23 October 2020 diff hist 0 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:41, 23 October 2020 diff hist +54 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:20, 23 October 2020 diff hist +1,309 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:09, 23 October 2020 diff hist +240 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:02, 22 October 2020 diff hist 0 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 17:58, 22 October 2020 diff hist 0 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 17:58, 22 October 2020 diff hist +99 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 17:57, 22 October 2020 diff hist -1 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 17:56, 22 October 2020 diff hist +35 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:15, 22 October 2020 diff hist +19 CIS Phase 1 work plans →Penetration Work
- 09:08, 22 October 2020 diff hist +48 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 14:15, 21 October 2020 diff hist +48 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 14:07, 21 October 2020 diff hist -428 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 14:03, 21 October 2020 diff hist +1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 09:33, 21 October 2020 diff hist -1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 09:30, 21 October 2020 diff hist +3 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:30, 21 October 2020 diff hist +15 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:29, 21 October 2020 diff hist +3 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:28, 21 October 2020 diff hist +927 CIS Phase 1 work plans →Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move GUn2 new location
- 09:15, 21 October 2020 diff hist -69 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:39, 20 October 2020 diff hist +1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:10, 20 October 2020 diff hist -3 CIS Phase 1 work plans
- 18:09, 20 October 2020 diff hist +1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:08, 20 October 2020 diff hist +5 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:06, 20 October 2020 diff hist +34 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:03, 20 October 2020 diff hist +76 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:01, 20 October 2020 diff hist +664 CIS Phase 1 work plans
- 17:57, 20 October 2020 diff hist +774 CIS Phase 1 work plans
- 17:50, 20 October 2020 diff hist +1 CIS Phase 1 work plans
- 17:49, 20 October 2020 diff hist -1 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:48, 20 October 2020 diff hist -3 CIS Phase 1 work plans →Fire System Work
- 17:48, 20 October 2020 diff hist +1 CIS Phase 1 work plans →Fire System Work
- 17:45, 20 October 2020 diff hist +3 CIS Phase 1 work plans →Fire System Work
- 17:44, 20 October 2020 diff hist +129 CIS Phase 1 work plans
- 17:41, 20 October 2020 diff hist -17 CIS Phase 1 work plans →Penetration Work
- 17:41, 20 October 2020 diff hist +1 CIS Phase 1 work plans →Penetration Work
- 17:41, 20 October 2020 diff hist +16 CIS Phase 1 work plans →Penetration Work
- 17:40, 20 October 2020 diff hist 0 N File:Firepipe 10 Oct Update.docx current
- 17:40, 20 October 2020 diff hist +64 CIS Phase 1 work plans →Penetration Work
- 17:37, 20 October 2020 diff hist +1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 17:36, 20 October 2020 diff hist +1,333 CIS Phase 1 work plans
- 17:30, 20 October 2020 diff hist +13 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:29, 20 October 2020 diff hist +36 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:27, 20 October 2020 diff hist -167 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:18, 20 October 2020 diff hist -23 CIS Phase 1 work plans
- 17:16, 20 October 2020 diff hist +190 CIS Phase 1 work plans
- 17:05, 20 October 2020 diff hist -22 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:04, 20 October 2020 diff hist 0 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:04, 20 October 2020 diff hist -9 CIS Phase 1 work plans →Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups
- 17:01, 20 October 2020 diff hist -7 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 17:00, 20 October 2020 diff hist -82 CIS Phase 1 work plans
- 16:58, 20 October 2020 diff hist +119 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 16:49, 20 October 2020 diff hist +43 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 16:37, 20 October 2020 diff hist +2 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 16:36, 20 October 2020 diff hist -2 CIS Phase 1 work plans
- 16:31, 20 October 2020 diff hist 0 N File:InjSB Week5.png current
- 16:19, 20 October 2020 diff hist +295 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 08:29, 20 October 2020 diff hist +363 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 18:21, 19 October 2020 diff hist +130 CEBAF Injector Upgrade →ATLIS Tasks
- 13:15, 19 October 2020 diff hist +142 CIS Phase 1 work plans →Fire System Work
- 13:10, 19 October 2020 diff hist +86 CIS Phase 1 work plans →Fire System Work
- 12:45, 19 October 2020 diff hist +26 CIS Phase 1 work plans
- 09:27, 16 October 2020 diff hist -35 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 08:59, 16 October 2020 diff hist +2 CIS Phase 1 work plans
- 17:10, 15 October 2020 diff hist 0 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:57, 15 October 2020 diff hist -14 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 16:55, 15 October 2020 diff hist -33 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:54, 15 October 2020 diff hist +9 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:54, 15 October 2020 diff hist -1 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:53, 15 October 2020 diff hist +306 CIS Phase 1 work plans
- 16:47, 15 October 2020 diff hist +414 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 09:07, 15 October 2020 diff hist +434 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 14:36, 14 October 2020 diff hist +111 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 14:25, 14 October 2020 diff hist +159 N Tunnel Photos Oct14 2020 Created page with " 1000px 1000px 1000px" current
- 14:22, 14 October 2020 diff hist +327 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 14:18, 14 October 2020 diff hist +1 CEBAF Injector Upgrade →Quick Links
- 14:17, 14 October 2020 diff hist 0 N File:Oct14 Chopper LookingUpstream.JPG current
- 14:17, 14 October 2020 diff hist 0 N File:Oct14 Ychamber LookingDownstream.JPG current
- 14:17, 14 October 2020 diff hist 0 N File:Oct14 Gun2 LookingDownstream.JPG current
- 14:13, 14 October 2020 diff hist +131 N Penetration135 Created page with "Entrance: IN03B17 Exit: Above middle of 0L03 cryomodule (first full zone) 1000px file:InjSB Racks.png"
- 14:12, 14 October 2020 diff hist +123 N Penetration108 Created page with "Entrance: IN03B04 Exit: Above harp IHA0L03, just before PSS fence 1000px file:InjSB Racks.png"
- 14:11, 14 October 2020 diff hist +121 N Penetration86 Created page with "Entrance: IN02B23 Exit: above MQJ0L02, just past plastic barrier 1000px file:InjSB Racks.png"
- 14:10, 14 October 2020 diff hist +107 N Penetration58 Created page with "Entrance: IN02B10 Exit: Above buncher cavity ~0I05 1000px File:InjSB Racks.png"
- 14:09, 14 October 2020 diff hist +1 PenetrationALH
- 14:08, 14 October 2020 diff hist +9 PenetrationALH
- 14:07, 14 October 2020 diff hist -1 PenetrationALH
- 14:06, 14 October 2020 diff hist +127 N PenetrationALH Created page with "Entrance: IN01B06 Exit: Above Laser hut, ~across for where Y-chamber would be. file:Pene108.JPG file:InjSB_Racks.png"
- 14:04, 14 October 2020 diff hist 0 N File:Pene108.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:Pene135.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:Pene86.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:PeneLH.JPG current
- 14:04, 14 October 2020 diff hist 0 N File:Pene58.JPG current
- 13:58, 14 October 2020 diff hist +75 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 13:57, 14 October 2020 diff hist +2 CIS Phase 1 work plans
- 13:56, 14 October 2020 diff hist +156 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 13:51, 14 October 2020 diff hist 0 File:InjSB Racks.png Moser uploaded a new version of File:InjSB Racks.png current
- 13:50, 14 October 2020 diff hist 0 File:InjSB Racks.png Moser uploaded a new version of File:InjSB Racks.png
- 13:50, 14 October 2020 diff hist 0 File:InjSB Racks.png Moser uploaded a new version of File:InjSB Racks.png
- 09:05, 14 October 2020 diff hist +1 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 09:04, 14 October 2020 diff hist +445 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 17:00, 13 October 2020 diff hist +3 CIS Phase 1 work plans →Week 5 (Oct 19 - Oct 23)
- 16:58, 13 October 2020 diff hist +135 CIS Phase 1 work plans
- 09:29, 13 October 2020 diff hist +358 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 20:11, 12 October 2020 diff hist +41 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18)
- 14:50, 12 October 2020 diff hist +52 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18)
- 14:35, 12 October 2020 diff hist +403 CIS Phase 1 work plans →Week 4 (Oct 12 - Oct 18)
- 14:32, 12 October 2020 diff hist 0 N File:InjSB Racks.png
- 14:28, 12 October 2020 diff hist +715 CIS Phase 1 work plans
- 09:00, 12 October 2020 diff hist +72 CEBAF Injector Upgrade →Quick Links
- 13:51, 9 October 2020 diff hist 0 File:Oct2020 Moser.odp Moser uploaded a new version of File:Oct2020 Moser.odp current
- 12:59, 9 October 2020 diff hist -1 Weekly phone call - October 9, 2020 →Agenda current
- 12:59, 9 October 2020 diff hist -41 Weekly phone call - October 9, 2020 →Agenda
- 12:59, 9 October 2020 diff hist +2 Weekly phone call - October 9, 2020 →Agenda
- 12:58, 9 October 2020 diff hist -1 Weekly phone call - October 9, 2020 →Agenda
- 12:58, 9 October 2020 diff hist +59 Weekly phone call - October 9, 2020 →Agenda
- 12:57, 9 October 2020 diff hist 0 N File:Oct2020 Moser.odp
- 08:13, 9 October 2020 diff hist +46 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 08:13, 9 October 2020 diff hist +63 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 08:10, 9 October 2020 diff hist +96 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:55, 7 October 2020 diff hist +125 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:54, 7 October 2020 diff hist -422 CIS Phase 1 work plans
- 19:49, 7 October 2020 diff hist +422 CIS Phase 1 work plans
- 19:20, 7 October 2020 diff hist +115 CEBAF Injector Upgrade →ATLIS Tasks
- 09:15, 7 October 2020 diff hist +212 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 09:12, 7 October 2020 diff hist -1 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 09:09, 7 October 2020 diff hist 0 N File:InjSB-Oct7th.png current
- 08:29, 7 October 2020 diff hist +28 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 08:28, 7 October 2020 diff hist 0 N File:InjSB-10.7.20.jpg current
- 08:03, 7 October 2020 diff hist +17 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:54, 6 October 2020 diff hist +3 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:53, 6 October 2020 diff hist -1 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:53, 6 October 2020 diff hist +5 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:52, 6 October 2020 diff hist +123 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 19:34, 6 October 2020 diff hist -3 CEBAF Injector Upgrade →ATLIS Tasks
- 13:00, 6 October 2020 diff hist 0 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 12:59, 6 October 2020 diff hist +4 Unknown Pene for Choppers current
- 12:59, 6 October 2020 diff hist +2 Unknown Pene for Choppers
- 12:58, 6 October 2020 diff hist +14 Unknown Pene for Choppers
- 12:58, 6 October 2020 diff hist -1 Unknown Pene for Choppers
- 12:57, 6 October 2020 diff hist +3 Unknown Pene for Choppers
- 12:56, 6 October 2020 diff hist 0 N File:Inj Pen2W.jpg current
- 12:55, 6 October 2020 diff hist 0 N File:Inj Pen1.jpg current
- 12:55, 6 October 2020 diff hist +42 N Unknown Pene for Choppers Created page with "File:Example.jpg File:Example.jpg"
- 12:54, 6 October 2020 diff hist +51 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 12:52, 6 October 2020 diff hist +106 CEBAF Injector Upgrade
- 08:27, 6 October 2020 diff hist +428 CIS Phase 1 work plans
- 17:06, 5 October 2020 diff hist +6 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 16:49, 5 October 2020 diff hist +1 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 16:49, 5 October 2020 diff hist +256 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 08:05, 5 October 2020 diff hist -1,113 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 08:05, 5 October 2020 diff hist +1,112 N Tue 9/29 – Fri 10/1 Table Created page with "; <u>'''Tunnel Work'''</u> {| class="wikitable" |- ! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2 |- | 4a - 8a || || I&C; 5a: Francis: BPMs, Cups, Apertu..." current
- 08:04, 5 October 2020 diff hist +2 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 08:04, 5 October 2020 diff hist -12 CIS Phase 1 work plans
- 08:55, 2 October 2020 diff hist +61 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 08:53, 2 October 2020 diff hist +29 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 08:51, 2 October 2020 diff hist +20 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 19:22, 1 October 2020 diff hist +20 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 19:18, 1 October 2020 diff hist +95 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 09:38, 1 October 2020 diff hist +135 CEBAF Injector Upgrade →ATLIS Tasks
- 08:59, 1 October 2020 diff hist +307 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 08:31, 1 October 2020 diff hist +114 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 08:03, 1 October 2020 diff hist +48 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 16:36, 30 September 2020 diff hist +24 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 16:35, 30 September 2020 diff hist +74 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 16:22, 30 September 2020 diff hist +73 CEBAF Injector Upgrade →ATLIS Tasks
- 08:59, 30 September 2020 diff hist +43 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 08:58, 30 September 2020 diff hist +43 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 08:57, 30 September 2020 diff hist +1 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 08:57, 30 September 2020 diff hist +442 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 08:17, 30 September 2020 diff hist +163 CEBAF Injector Upgrade →ATLIS Tasks
- 09:52, 29 September 2020 diff hist +4 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 09:50, 29 September 2020 diff hist +9 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 09:50, 29 September 2020 diff hist +1 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 09:49, 29 September 2020 diff hist +318 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 09:35, 29 September 2020 diff hist +93 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 08:17, 29 September 2020 diff hist +50 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 17:30, 28 September 2020 diff hist +50 CIS Phase 1 work plans
- 15:02, 28 September 2020 diff hist +534 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 14:24, 28 September 2020 diff hist +103 CEBAF Injector Upgrade →ATLIS Tasks
- 12:28, 28 September 2020 diff hist +232 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 12:21, 28 September 2020 diff hist +129 CEBAF Injector Upgrade →ATLIS Tasks
- 10:32, 28 September 2020 diff hist +96 CEBAF Injector Upgrade →ATLIS Tasks
- 09:32, 28 September 2020 diff hist +20 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 09:32, 28 September 2020 diff hist +21 CIS Phase 1 work plans →Week 3 (Oct 5 - Oct 11)
- 09:30, 28 September 2020 diff hist +474 CIS Phase 1 work plans →Week 2 (Sep 28 - Oct 4)
- 15:29, 22 September 2020 diff hist +33 UITC Operations
- 23:41, 18 January 2020 diff hist +395 Archived Documents →2017
- 14:11, 11 October 2019 diff hist 0 N File:12GeV injector quick reference rev16.pdf current
- 14:11, 11 October 2019 diff hist -17 Main Page
- 11:00, 25 September 2019 diff hist 0 Main Page →Group Links
- 10:59, 25 September 2019 diff hist 0 N File:12GeV injector quick reference rev16 beta.pdf current
- 10:59, 25 September 2019 diff hist +28 Main Page →Group Links
- 14:26, 19 December 2018 diff hist +92 2018 Mott Paper Working Area →Request #7 -- Absolute Calibration of BCM0L02 to FC#2 current
- 14:23, 19 December 2018 diff hist 0 N File:Run2 0L02 v FC2.gif current
- 14:23, 19 December 2018 diff hist 0 N File:Run2 Mott v 0L02.gif current
- 16:07, 9 December 2018 diff hist -1 2018 Mott Paper Working Area →Request #7 -- Absolute Calibration of BCM0L02 to FC#2
- 16:05, 9 December 2018 diff hist +13 2018 Mott Paper Working Area →Request #7 -- Absolute Calibration of BCM0L02 to FC#2
- 15:47, 9 December 2018 diff hist -7 2018 Mott Paper Working Area →Request #7 -- Absolute Calibration of BCM0L02 to FC#2
- 15:46, 9 December 2018 diff hist +542 2018 Mott Paper Working Area →Request #7 -- Absolute Calibration of BCM0L02 to FC#2
- 15:40, 9 December 2018 diff hist 0 N File:Run1 VtoF v 0L02.gif current
- 15:39, 9 December 2018 diff hist 0 N File:Run1 BCM0L02 v FC2.gif current
- 12:51, 15 November 2018 diff hist +147 2018 Mott Paper Working Area →Request #8 -- Comparison of Absolute Detector Rate to Measured Detector Rate
- 12:46, 15 November 2018 diff hist 0 N File:RunI RunII RvT FitParameters.ods current
- 12:45, 15 November 2018 diff hist 0 N File:RunII DetectorRates v Thickness.gif current
- 12:45, 15 November 2018 diff hist 0 N File:RunI DetectorRates v Thickness.gif current
- 14:32, 14 November 2018 diff hist +101 2018 Mott Paper Working Area →Request #8 -- Comparison of Absolute Detector Rate to Measured Detector Rate
- 14:23, 14 November 2018 diff hist 0 File:11.14.18 RunI RunII NormalizedRates.ods Moser uploaded a new version of File:11.14.18 RunI RunII NormalizedRates.ods current
- 14:23, 14 November 2018 diff hist 0 N File:RunII NormalizedRates Average.gif current
- 14:22, 14 November 2018 diff hist 0 N File:RunII NormalizedRates byDetector.gif current
- 13:46, 14 November 2018 diff hist +53 2018 Mott Paper Working Area
- 13:45, 14 November 2018 diff hist 0 N File:11.14.18 RunI RunII NormalizedRates.ods
- 12:41, 14 November 2018 diff hist +13 2018 Mott Paper Working Area →Request #7 -- Absolute Calibration of BCM0L02 to FC#2
- 12:39, 14 November 2018 diff hist 0 2018 Mott Paper Working Area →Request #7 -- Absolute Calibration of BCM0L02 to FC#2
- 12:36, 14 November 2018 diff hist +954 2018 Mott Paper Working Area →Request #7 -- Absolute Calibration of BCM0L02 to FC#2
- 14:33, 8 November 2018 diff hist +202 2018 Mott Paper Working Area →General Links/Documents
- 14:21, 8 November 2018 diff hist -33 2018 Mott Paper Working Area →General Links/Documents
- 14:20, 8 November 2018 diff hist +4 2018 Mott Paper Working Area →General Links/Documents
- 14:19, 8 November 2018 diff hist +811 2018 Mott Paper Working Area →General Links/Documents
- 15:53, 4 November 2018 diff hist -84 2018 Mott Paper Working Area →General Links/Documents
- 15:49, 4 November 2018 diff hist +108 2018 Mott Paper Working Area →Draft Punchlist
- 15:48, 4 November 2018 diff hist +20 2018 Mott Paper Working Area →Request #2
- 15:47, 4 November 2018 diff hist +11 2018 Mott Paper Working Area →Request #1 -- First Draft Below
- 15:46, 4 November 2018 diff hist 0 N File:Asym v beampos 1000.gif current
- 15:46, 4 November 2018 diff hist 0 N File:Asym v beampos 225.gif current
- 15:46, 4 November 2018 diff hist 0 N File:Asym v beampos final.ods current
- 14:04, 4 November 2018 diff hist -54 2018 Mott Paper Working Area →Request #2
- 13:56, 4 November 2018 diff hist -1 2018 Mott Paper Working Area →Request #1 -- First Draft Below