09:39 | CIS Phase 1 work plans (8 changes | history) . . (+554) . . [Moser (8×)] | |
09:39 (cur | prev) . . (0) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) | ||
09:21 (cur | prev) . . (+2) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) | ||
09:19 (cur | prev) . . (+85) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) | ||
09:16 (cur | prev) . . (+57) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) | ||
09:05 (cur | prev) . . (+253) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) | ||
08:28 (cur | prev) . . (+9) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) | ||
08:27 (cur | prev) . . (+41) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) | ||
08:19 (cur | prev) . . (+107) . . Moser (Talk | contribs) (→Week 28 (Apr 12 - Apr 16)) |
N 09:33 | GTS meeting 4 12 21 (6 changes | history) . . (+892) . . [Suleiman (6×)] | |
09:33 (cur | prev) . . (+6) . . Suleiman (Talk | contribs) | ||
09:21 (cur | prev) . . (+45) . . Suleiman (Talk | contribs) | ||
09:12 (cur | prev) . . (-8) . . Suleiman (Talk | contribs) | ||
09:10 (cur | prev) . . (-312) . . Suleiman (Talk | contribs) | ||
09:10 (cur | prev) . . (+102) . . Suleiman (Talk | contribs) | ||
N | 09:08 (cur | prev) . . (+1,059) . . Suleiman (Talk | contribs) (Created page with "* Upgrade Glassman Gun PSS interlock chassis (Scott) * Add vacuum interlock to HV supply (Scott) Plan B: Install Spellman 225 kV power supply. Did not work because we could n...") |
09:08 | Gun Test Stand Meeting Minutes and To-Do Lists (diff | hist) . . (+63) . . Suleiman (Talk | contribs) |
08:57 | (Upload log) . . [Chgarcia (2×)] | |
08:57 . . Chgarcia (Talk | contribs) uploaded File:Horizontal Wien Integrals (19.9A Hyst) with SCE410 CORRECT Ni plates.xlsx | ||
08:56 . . Chgarcia (Talk | contribs) uploaded File:Vertical Wien Integrals (19.9A Hyst) with SCE410.xlsx |
08:56 | WF Wien Filters (200 kV upgrade) (diff | hist) . . (+170) . . Chgarcia (Talk | contribs) |