Difference between revisions of "UITF Meeting - January 29, 2018"

From Ciswikidb
Jump to navigation Jump to search
 
(2 intermediate revisions by one other user not shown)
Line 7: Line 7:
  
 
*Choppers are being conditioned by Mark and Larry. Thanks!  
 
*Choppers are being conditioned by Mark and Larry. Thanks!  
*When do you estimate to complete conditioning for 200 keV beam (75 Watts RF power on choppers).
+
** What is status of 1X/1Y and 2X/2Y?
 +
**When do you estimate to complete conditioning for 200 keV beam (75 Watts RF power on choppers), '''at least 1X/2X'''
 +
**We'll need screens/guidance to operate choppers - how's that going?
  
 
*Magnets:  
 
*Magnets:  
Line 19: Line 21:
  
 
*FSD
 
*FSD
**Performed software functionality test in UITF control room last week. What else is needed for full functionality?
+
**Performed software functionality test in UITF control room last week.  
 +
**What else is needed for full functionality?
 +
 
  
 
*BPMs
 
*BPMs
 
**Cables installed and terminated.
 
**Cables installed and terminated.
 
**Status on hardware, firmware, and EPICS software?
 
**Status on hardware, firmware, and EPICS software?
 +
** We need them operational and reading in EPICS before running beam in Tune Mode
  
 
*CRYO
 
*CRYO
**From last meeting: Cool down transfer line and 1/4 cryo-module to 80 K. Any updates?
+
**From last meeting: Cool down transfer line and 1/4 cryo-module to 80 K.
**Estimate time to complete?
+
**Estimated time to complete?
 +
** Update: D. Bullard completed installation of guard vacuum relief vent outside the cave
 +
** UPDATES: cryogenic connections?
  
 
*RF
 
*RF
 
**Update on RF for Quarter Cryo Module?
 
**Update on RF for Quarter Cryo Module?
 
**Estimate time to complete?
 
**Estimate time to complete?
 +
** UPDATES: Klystron connections?
  
  

Latest revision as of 09:42, 29 January 2018


200keV Beam to both UITF dumps!


UITF Schedule - Zimbra calendar resource now functional. Add uitf-schedule to your zimbra calendar to see cae lock-up dates/times, etc.


UPDATES

  • Choppers are being conditioned by Mark and Larry. Thanks!
    • What is status of 1X/1Y and 2X/2Y?
    • When do you estimate to complete conditioning for 200 keV beam (75 Watts RF power on choppers), at least 1X/2X
    • We'll need screens/guidance to operate choppers - how's that going?
  • Valves
    • When will the two MDC valves have status read back?
  • FSD
    • Performed software functionality test in UITF control room last week.
    • What else is needed for full functionality?


  • BPMs
    • Cables installed and terminated.
    • Status on hardware, firmware, and EPICS software?
    • We need them operational and reading in EPICS before running beam in Tune Mode
  • CRYO
    • From last meeting: Cool down transfer line and 1/4 cryo-module to 80 K.
    • Estimated time to complete?
    • Update: D. Bullard completed installation of guard vacuum relief vent outside the cave
    • UPDATES: cryogenic connections?
  • RF
    • Update on RF for Quarter Cryo Module?
    • Estimate time to complete?
    • UPDATES: Klystron connections?


Epics screens Working with T. Larrieu and team on SAVE/RESTORE.

Matt is working on OSP for buncher and choppers


By February 5, 2018:

All cryo work complete All High Power RF work complete OSP for QCM approved ODH assessment, vent can on relief stack, penetrations filled, etc,