UITF Meeting - January 29, 2018

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

200keV Beam to both UITF dumps!


UITF Schedule - Zimbra calendar resource now functional. Add uitf-schedule to your zimbra calendar to see cae lock-up dates/times, etc.


UPDATES

  • Choppers are being conditioned by Mark and Larry. Thanks!
    • What is status of 1X/1Y and 2X/2Y?
    • When do you estimate to complete conditioning for 200 keV beam (75 Watts RF power on choppers), at least 1X/2X
    • We'll need screens/guidance to operate choppers - how's that going?
  • Valves
    • When will the two MDC valves have status read back?
  • FSD
    • Performed software functionality test in UITF control room last week.
    • What else is needed for full functionality?


  • BPMs
    • Cables installed and terminated.
    • Status on hardware, firmware, and EPICS software?
    • We need them operational and reading in EPICS before running beam in Tune Mode
  • CRYO
    • From last meeting: Cool down transfer line and 1/4 cryo-module to 80 K.
    • Estimated time to complete?
    • Update: D. Bullard completed installation of guard vacuum relief vent outside the cave
    • UPDATES: cryogenic connections?
  • RF
    • Update on RF for Quarter Cryo Module?
    • Estimate time to complete?
    • UPDATES: Klystron connections?


Epics screens Working with T. Larrieu and team on SAVE/RESTORE.

Matt is working on OSP for buncher and choppers


By February 5, 2018:

All cryo work complete All High Power RF work complete OSP for QCM approved ODH assessment, vent can on relief stack, penetrations filled, etc,