(Created page with " ---- Tasks before running beam to HDIce for target commissioning ---- Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and compan...")
 
Line 6: Line 6:
  
  
Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)
+
# Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)
  
2) Vacuum Group, build the MeV beamline
+
# Vacuum Group, build the MeV beamline
  
3) Cryo: install the helium return line
+
# Cryo: install the helium return line
  
4) SRF, need a point of contact for all things related to QCM operation
+
# SRF, need a point of contact for all things related to QCM operation
  
5) Electrical engineering: design and build the PSS BCM
+
# Electrical engineering: design and build the PSS BCM
  
6) Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)
+
# Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)
  
7) Magnet group: give us a third trim card rack
+
# Magnet group: give us a third trim card rack
  
8) RF group: klystrons, high power amplifier, solid state amp, water skids
+
# RF group: klystrons, high power amplifier, solid state amp, water skids
  
9) Vashek: finish specifying the shielding requirements, then we start moving lead
+
# Vashek: finish specifying the shielding requirements, then we start moving lead
  
10) R&D related to low current BPMs, suggest you take that on, with help from Engineering
+
# R&D related to low current BPMs, suggest you take that on, with help from Engineering
  
11) Operations Group should augment Joe's modeling, using a particle tracking code
+
# Operations Group should augment Joe's modeling, using a particle tracking code
  
12) Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review
+
# Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review
  
13) Gun group needs to build a new photogun
+
# Gun group needs to build a new photogun
  
14) Need to operate the UITF on a daily basis.....
+
# Need to operate the UITF on a daily basis.....

Revision as of 12:37, 13 June 2018


Tasks before running beam to HDIce for target commissioning



  1. Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)
  1. Vacuum Group, build the MeV beamline
  1. Cryo: install the helium return line
  1. SRF, need a point of contact for all things related to QCM operation
  1. Electrical engineering: design and build the PSS BCM
  1. Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)
  1. Magnet group: give us a third trim card rack
  1. RF group: klystrons, high power amplifier, solid state amp, water skids
  1. Vashek: finish specifying the shielding requirements, then we start moving lead
  1. R&D related to low current BPMs, suggest you take that on, with help from Engineering
  1. Operations Group should augment Joe's modeling, using a particle tracking code
  1. Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review
  1. Gun group needs to build a new photogun
  1. Need to operate the UITF on a daily basis.....