# Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)
 
# Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)
 
 
# Vacuum Group, build the MeV beamline
 
# Vacuum Group, build the MeV beamline
 
 
# Cryo: install the helium return line
 
# Cryo: install the helium return line
 
 
# SRF, need a point of contact for all things related to QCM operation
 
# SRF, need a point of contact for all things related to QCM operation
 
 
# Electrical engineering: design and build the PSS BCM
 
# Electrical engineering: design and build the PSS BCM
 
 
# Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)
 
# Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)
 
 
# Magnet group: give us a third trim card rack
 
# Magnet group: give us a third trim card rack
 
 
# RF group: klystrons, high power amplifier, solid state amp, water skids
 
# RF group: klystrons, high power amplifier, solid state amp, water skids
 
 
# Vashek: finish specifying the shielding requirements, then we start moving lead
 
# Vashek: finish specifying the shielding requirements, then we start moving lead
 
 
# R&D related to low current BPMs, suggest you take that on, with help from Engineering
 
# R&D related to low current BPMs, suggest you take that on, with help from Engineering
 
 
# Operations Group should augment Joe's modeling, using a particle tracking code
 
# Operations Group should augment Joe's modeling, using a particle tracking code
 
 
# Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review
 
# Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review
 
 
# Gun group needs to build a new photogun
 
# Gun group needs to build a new photogun
 
 
# Need to operate the UITF on a daily basis.....
 
# Need to operate the UITF on a daily basis.....

Revision as of 12:38, 13 June 2018


Tasks before running beam to HDIce for target commissioning



  1. Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)
  2. Vacuum Group, build the MeV beamline
  3. Cryo: install the helium return line
  4. SRF, need a point of contact for all things related to QCM operation
  5. Electrical engineering: design and build the PSS BCM
  6. Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)
  7. Magnet group: give us a third trim card rack
  8. RF group: klystrons, high power amplifier, solid state amp, water skids
  9. Vashek: finish specifying the shielding requirements, then we start moving lead
  10. R&D related to low current BPMs, suggest you take that on, with help from Engineering
  11. Operations Group should augment Joe's modeling, using a particle tracking code
  12. Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review
  13. Gun group needs to build a new photogun
  14. Need to operate the UITF on a daily basis.....