Tasks before running beam to HDIce for target commissioning



Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)

2) Vacuum Group, build the MeV beamline

3) Cryo: install the helium return line

4) SRF, need a point of contact for all things related to QCM operation

5) Electrical engineering: design and build the PSS BCM

6) Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)

7) Magnet group: give us a third trim card rack

8) RF group: klystrons, high power amplifier, solid state amp, water skids

9) Vashek: finish specifying the shielding requirements, then we start moving lead

10) R&D related to low current BPMs, suggest you take that on, with help from Engineering

11) Operations Group should augment Joe's modeling, using a particle tracking code

12) Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review

13) Gun group needs to build a new photogun

14) Need to operate the UITF on a daily basis.....