(Created page with "Back to Run Group F | Daily Run Group F Coordination Meetings 10:00AM Run Meeting, Counting house meeting room (200C) '''RC:''' Carlos Ayerbe ==Summary...") |
(→Plan:) |
||
(One intermediate revision by the same user not shown) | |||
Line 7: | Line 7: | ||
==Summary of past 24h:== | ==Summary of past 24h:== | ||
− | * | + | * Summary in the RC Daily Report |
− | + | https://logbooks.jlab.org/entry/3806359 | |
+ | * HV issues (https://logbooks.jlab.org/entry/3806487): | ||
+ | ** in order to run cosmic, we tweak the HV GUI to short the delay time to ramp up the GEM voltage and reduce the cathode to -5500V | ||
+ | ** we were able to run op to -5600 (I guess Mohammad raised to -5650 and later in the night to -6100V but not sure when) | ||
+ | ** From the strip chart it is clear the RTPC trips around 04:30 [[File:Clonpc14 20200320 085446.gif]] | ||
+ | ==Plan:== | ||
+ | |||
+ | * Nate D. notice that the drift pressure was low (02:45), and no bubbles. I checked the gas shed and the manometer indicates 10psig in the pre-mix lines. We need to check that. | ||
+ | |||
+ | [[File:Image.png|400px]] | ||
− | + | * BPM alignment ongoing. | |
− | * | + | * Jiwan and Nathan B. should take a decision of the HV modules (keep in Yuri's crate, return to the original, make changes in software...?) |
− | * | + | * Install bubblers camera. |
+ | * turn on blower (sucker). | ||
+ | * RadCon to move RTPC1 to EEL bldg. | ||
+ | * From Eugene: | ||
+ | '''What magnetic field configuration are we going to start with? Torus Inbending? outbending? Solenoid polarity and strength? ''' | ||
+ | * According to Sebastian, Stepan will help to set physics beam. | ||
+ | * My ETA to have Hall ON, ~11:00 | ||
==Slides== | ==Slides== |
Latest revision as of 08:20, 20 March 2020
Back to Run Group F | Daily Run Group F Coordination Meetings
10:00AM Run Meeting, Counting house meeting room (200C)
RC: Carlos Ayerbe
Summary of past 24h:
- Summary in the RC Daily Report
https://logbooks.jlab.org/entry/3806359
- HV issues (https://logbooks.jlab.org/entry/3806487):
- in order to run cosmic, we tweak the HV GUI to short the delay time to ramp up the GEM voltage and reduce the cathode to -5500V
- we were able to run op to -5600 (I guess Mohammad raised to -5650 and later in the night to -6100V but not sure when)
- From the strip chart it is clear the RTPC trips around 04:30
Plan:
- Nate D. notice that the drift pressure was low (02:45), and no bubbles. I checked the gas shed and the manometer indicates 10psig in the pre-mix lines. We need to check that.
- BPM alignment ongoing.
- Jiwan and Nathan B. should take a decision of the HV modules (keep in Yuri's crate, return to the original, make changes in software...?)
- Install bubblers camera.
- turn on blower (sucker).
- RadCon to move RTPC1 to EEL bldg.
- From Eugene:
What magnetic field configuration are we going to start with? Torus Inbending? outbending? Solenoid polarity and strength?
- According to Sebastian, Stepan will help to set physics beam.
- My ETA to have Hall ON, ~11:00
Slides
Info
BlueJeans connection info:
To join the Meeting: https://bluejeans.com/7576835804