Difference between revisions of "Run Meeting: August 11th, 2020"
Jump to navigation
Jump to search
(Created page with "==Summary of past 24h:== Monday, August 10 to Tuesday, August 11 5-pass data taking at 200 nA on deuterium (about 63 M events). Reasonable data taking with good beam for th...") |
|||
(2 intermediate revisions by the same user not shown) | |||
Line 10: | Line 10: | ||
Special RTPC HV test runs taken during the night shift (Mohammad): | Special RTPC HV test runs taken during the night shift (Mohammad): | ||
− | |||
− | |||
− | |||
− | + | 2:47 12478 10.5 M events (GEM amplification HV was 385 V) | |
+ | 4:19 12479 6.6 M events (GEM amplification HV was 375 V) | ||
+ | 7:58 12480 5.4 M events (GEM amplification HV was 365 V) | ||
+ | |||
+ | The regular GEM amplification HV is 390 V. | ||
+ | |||
+ | '''Plan for next 24 hours''' | ||
Maintenance during the day shift. | Maintenance during the day shift. | ||
+ | |||
Data taking afterwards. | Data taking afterwards. |
Latest revision as of 08:52, 11 August 2020
Summary of past 24h:
Monday, August 10 to Tuesday, August 11
5-pass data taking at 200 nA on deuterium (about 63 M events).
Reasonable data taking with good beam for the most part, but relatively many RF trips at other times.
Deuterium target purged opportunistically at 11 AM on Monday and 6 AM on Tuesday.
Special RTPC HV test runs taken during the night shift (Mohammad):
2:47 12478 10.5 M events (GEM amplification HV was 385 V) 4:19 12479 6.6 M events (GEM amplification HV was 375 V) 7:58 12480 5.4 M events (GEM amplification HV was 365 V)
The regular GEM amplification HV is 390 V.
Plan for next 24 hours
Maintenance during the day shift.
Data taking afterwards.