Difference between revisions of "Run Meeting: August 13th, 2020"
Jump to navigation
Jump to search
(Created page with "Back to Run Group F | Daily Run Group F Coordination Meetings 10:00AM Run Meeting, <s>Counting house meeting room (200C)</s> ONLINE '''RC:''' Carlos Ayer...") |
|||
(2 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
Back to [[Run Group F|Run Group F]] | [[Daily Run Group F Coordination Meetings]] | Back to [[Run Group F|Run Group F]] | [[Daily Run Group F Coordination Meetings]] | ||
− | + | 12:00PM Run Meeting, <s>Counting house meeting room (200C)</s> ONLINE | |
'''RC:''' Carlos Ayerbe | '''RC:''' Carlos Ayerbe | ||
==Summary of past 24h:== | ==Summary of past 24h:== | ||
+ | |||
+ | RC report from Stephen: https://logbooks.jlab.org/entry/3825827 | ||
+ | |||
+ | '''Shifters summary''':<br /> | ||
+ | |||
+ | Day: https://logbooks.jlab.org/entry/3825613<br /> | ||
+ | Swing:https://logbooks.jlab.org/entry/3825902<br /> | ||
+ | Owl: https://logbooks.jlab.org/entry/3826129<br /> | ||
+ | |||
+ | |||
+ | * Electric storm caused some beam delays (https://logbooks.jlab.org/entry/3825867)<br /> | ||
+ | * Deuterium bottle was changed. It was reported a possible issue with the high pressure gauge, but nothing critical. <br /> | ||
+ | * Valery K, requested to change the trigger configuration file as was agreed early. '''Note:''' sometimes, the GUI won't show the uploaded trigger file, here is the simple solution: https://logbooks.jlab.org/entry/3825867 | ||
+ | * Mohammad requested an increase of current from 200nA to 240nA for testing purposes (just one run, ~ 05:30). | ||
+ | * Due to beam studies, beam will be down for 2 hours (09-11:00). It was finished early. | ||
+ | |||
+ | ==Plan:== | ||
+ | |||
+ | Continue taking data. | ||
==Info== | ==Info== |
Latest revision as of 10:41, 13 August 2020
Back to Run Group F | Daily Run Group F Coordination Meetings
12:00PM Run Meeting, Counting house meeting room (200C) ONLINE
RC: Carlos Ayerbe
Summary of past 24h:
RC report from Stephen: https://logbooks.jlab.org/entry/3825827
Shifters summary:
Day: https://logbooks.jlab.org/entry/3825613
Swing:https://logbooks.jlab.org/entry/3825902
Owl: https://logbooks.jlab.org/entry/3826129
- Electric storm caused some beam delays (https://logbooks.jlab.org/entry/3825867)
- Deuterium bottle was changed. It was reported a possible issue with the high pressure gauge, but nothing critical.
- Valery K, requested to change the trigger configuration file as was agreed early. Note: sometimes, the GUI won't show the uploaded trigger file, here is the simple solution: https://logbooks.jlab.org/entry/3825867
- Mohammad requested an increase of current from 200nA to 240nA for testing purposes (just one run, ~ 05:30).
- Due to beam studies, beam will be down for 2 hours (09-11:00). It was finished early.
Plan:
Continue taking data.
Info
BlueJeans connection info:
To join the Meeting: https://bluejeans.com/7576835804