RGM RC Meeting Dec1 Dec7

From clas12-run
Revision as of 15:25, 2 December 2021 by Schmidta (talk | contribs)
Jump to navigation Jump to search

Thursday, December 2, 2021

  • Last 24 hours
    • RF Recovery Day
    • 20:30 Began restablishing beam to the Hall
    • 10:45 Resumed production Running
    • Overnight DAQ issues
    • 04:00 - 08:00 Beam down due to blown fuse (| Logbook entry)
    • More DAQ Issues in the morning
    • 11:10 Stable running again
  • Updated monitoring reference run to 15283 (from today)
  • DAQ Issues
  • MVT Trips
  • Question of DC Sector 1 Occupancies before Wednesday
  • Short-term plan
    • As of yesterday, plan was to switch to Sn on Friday afternoon, Ca on Monday.
      • Denny Insley plans to call for restricted access at 7:30 AM (Mon. 12/6), with goal to start work by 8:15 AM, finish by around the end of the day shift.
    • Any changes to this plan?
    • Any calibrations still needed on C (low current runs, etc.)?
  • Analysis Meeting to follow

Wednesday, December 1, 2021

  • RC Change-over
  • Re-establishing beam this afternoon/evening
  • Short-term run plan