03/08/2017 Meeting

From Cryowiki
Jump to navigationJump to search

Attendance

Thompson, Creel, Dixon, Michalski, Arenius


Agenda and Notes

1. Operations


LINAC

Normal

C100 heaters are in independent mode. We have been working with Arne to lower the North LINAC pressure following a test plan. We have moved in two 0.0005 steps. We are now at 0.038atm. CC4 has slowed by 20 HZ to ~540HZ.

CHL1

Normal

CHL2

Normal


ESR

Hall C believes the high SHMS back pressure is because of the flexible anaconda. Hall C changed the anaconda but it did not help. Transferline flow has been redirected from dewar to Hall supply to shore up 3atm pressure. More tuning for this mode is needed.


CTF

The CTF shutdown is underway.


HDR

Normal.


2. Projects

UIM

Shutdown is underway.


UITF

Thermosiphon is being fabricated.


MSU

Working to accumulate the pressure systems documentation. Meeting with Fabio. Mark Stapleton might make a trip to MSU at some point to teach their technicians.


LCLS2

2K review is next week and Hanley Lee. Still waiting on materials to be posted. Recovery compressors will be finished sometime in July.


3. Manpower

Ritendra is working on LCLS2. Duties need more definition. He is currently helping them catch up on controls tasks. There will be a 75% review of the installation package by Smith Group on 28 March.


4. Info from Will

1. LN2 contract proposals are in and have been routed to DOE for approval. The existing contract has been extended again.

2. New director starts Apr 3.

3. We have been asked to provide a feasibility study for putting an LCLS2 module in LERF.

4. Have the tool box meeting on the acid incident.


They have pushed the ESR2 money to 18'. There was talk in lab leadership meeting about putting a line item in for a new 2K cold box.


5. Other

Action Items

1. Must keep meeting to no more than 30 minutes

2. Plan the replacement of the SC2 power feedthrus.


Action Item Updates

1.

2.