03/23/2017 Meeting

From Cryowiki
Jump to navigationJump to search

Attendance

Thompson, Creel, Dixon, Oren, Arenius

Michalski on leave


Agenda and Notes

1. Operations


LINAC

Both LINACS at 4K


CHL1

Appears CC5 has suffered a failure. We have completed testing the bearing cabinet and did not find any problems. We are working a plan to disconnect the SC1 and warm it up so we can access and evaluate the failure. We have also requested Air Liquide complete the repair of CC4 and send it back as quickly as possible. They are estimating arrival at JLAB around 24 May. Utubes for the SC1 are planned in approximately 2 weeks because our tanks are full. Operations is working to off load helium back to Hall C and CTF to clear space.


CHL2


ESR

Hall C sent all of their liquid back to CHL so they could warm and purge their transferline. They have also reinstalled the original anaconda. Purge procedures are suspect. Hall A target utubes were removed to support them performing summer work. We will use the Hall C target to add the extra load. We have planned a load test as soon as soon as Hall C gets their magnets recooled.


CTF

The CTF shutdown is underway. The mechanical work is complete. Leak checks are complete. Pressure testing is planned for today. Controls are scheduled to be finished by Sunday. It is likely the restart will take more time because of retraining PIDs and offsets in temperature readings.


HDR

Normal. Hall D has approached us about transitioning the magnet to 80K which would also allow us to perform maintenance such as clean up and working on the turbine inlet valve.


2. Projects

UIM

The CTF shutdown is underway. The mechanical work is complete. They are working on leak checks, pressure tests, and continuing with the control system conversion.


UITF

Thermosiphon is being fabricated. There is a significant amount of controls work left to be done before this system can be made operational. We will likely start the controls work after the C6 installation.


MSU

We sent a compressor alignment package to Fabio.


LCLS2

Recovery compressors on track for July. Still have not seen drawings for water skid. Dana gave a re-plan to LCLS2 project management.


3. Manpower

4. Info from Will

1. New director starts Apr 3.

2. They have pushed the ESR2 money to at least 18' and the replacement for SC1 might be put on the list ahead.


5. Other

Action Items

1. 2L17 had a suspected vacuum leak. They used words like all eight tuners are frozen.

2.



Action Item Updates

1.

2.