04/13/2017 Meeting
Attendance
Thompson, Creel, Dixon, Oren, Michalski, Arenius
Agenda and Notes
1. Operations
LINAC
Both LINACS at 4K
CHL1
We are managing inventory to position ourselves to start the warm up of the SC1.
CHL2
Has been shutdown and plant is being positioned for C6 work and electrical panel maintenance to be starter Monday. Our ETechs will also perform maintenance on our equipment during this time.
ESR
We are recooling Hall C. Transferline will be available after CHL utubes. We are planning to perform the ESR load test.
CTF
The CTF UIM work is complete. We are working to restart the plant at this time. We fully expect to find and correct control system issues along the way.
HDR
Normal. Hall D has approached us about transitioning the magnet to 80K which would also allow us to perform maintenance such as clean up and working on the turbine inlet valve. We will rebuild the turbine inlet valve while we are down and replace the actuator. Will also perform pressure calibrations, electrical equipment and panel maintenance, etc.
2. Projects
UIM
The CTF shutdown is complete. We fully expect to find and correct control system issues along the way. The 3" Linde ball valve does not seal so we are going to blank it off and restart the plant. A plan to fix the valve will be planned and coordinated.
UITF
Thermosiphon is being fabricated. There is a significant amount of controls work left to be done before this system can be made operational. We will likely start the controls work after the C6 installation.
MSU
We sent a compressor alignment package to Fabio. We are expecting Mark Stapleton to make a 1 week trip to MSU.
LCLS2
Recovery compressors on track for July. Still have not seen drawings for water skid. Dana gave a re-plan to LCLS2 project management.
3. Manpower
4. Info from Will
1. New director started Apr 3.
2. They have pushed the ESR2 money to at least 2018 and the replacement for SC1 might be put on the list ahead.
3. Nusair studying SC1 4-stage operation.
5. We are moving forward on engineering and design for SC1 (and ESR2)
5. Other
Action Items
1.
2.
Action Item Updates
1.
2.