Meeting - Sep 07, 2017
From Cryowiki
Jump to navigationJump to searchAttenders: Kelly Dixon, Thilan Wijeration, Shirley Yang
1. Kinney # 2 was relocated to the right location on Aug. 23, 2017. 2. Thilan got a quote of the oil mist eliminator. But it only can handle 1200 CFM flow. Two are required for each Kinney system to meet the capacity requirement. 3. The blower and ring pump heat exchangers were flipped over. Willy can make the branches of the cooling water to Kinney #2 system. 4. Kinney #2 suction line has been completed installed. The discharge has to be stopped from the oil knock-out drum until the new coalescer is determined. 5. Corey is going to help John to generate the 3D conduit and cable trays to handle it to outside contractor for the work.