Meeting Mar 13, 2017
Attendance
Creel, Dixon, Scanlon, Oren,
Bevins, Arenius attending an LCLS2 re-baseline meeting
Agenda and Notes
1. Manpower
Ritendra is working the electrical and controls package.
2. Project
The 2K FDR was 9 Mar at JLAB. Reviewers have not produced a report yet but feeling is they are not at 90% design.
Internal 2K piping is being worked with Hung yu and Damon Rath.
Smith groups review of the installation package is complete.
Mike reports the upstream can design is almost complete and they are working on the downstream can.
3. Recovery Compressor Progress
Heat exchanges did not show up on time. When Ski called, the vendor indicated the ship date slipped one month. ITT is running three shifts to catch up.
4. Additional work
There is more potential fabrication work for a turbine and cold compressor water skid but we have not heard anything else.
There may also be some work building 230 bayonets, etc.
We met with Ed Daly to help him produce an estimate for the LCLS2 in LERF cryomodule testing. Daly estimated it would be required in 3-6 months. We agreed that he could use his end-can as is.
Action Items
1. Kelly needs a list of duties expected to support LCLS2 for Ritendra and Swapnil.