(Created page with "Attendance Nusair, Dixon, Thompson, Creel, Radovic, Dixon, Butler, Radovic, Wijeratne, Norton, Laverdure , Schleeper, Yang, Perry, Goals The purpose of this weekly meeting...")
 
 
(4 intermediate revisions by the same user not shown)
Line 14: Line 14:
  
  
 +
2. Schedule
  
2. Schedule
+
Plan is to run CHL1 and CHL2 at 2K until mid March.
  
 
      
 
      
 
3. JLAB Internal Group Projects
 
3. JLAB Internal Group Projects
  
 +
'''GPP (Yang, Thilan)'''
  
 +
Kinney Pump Relocation
  
  
GPP (Yang, Thilan)
+
Main Gas and Recovery Gas Management Systems
  
'''Kinney Pump Relocation'''
 
* Detailed design of Kinney suction and discharge piping system was completed.
 
* The material for Kinney suction has been received. The material for Kinney discharge has ordered.
 
* Started the detailed design package of the cooling water system.
 
* The actual design hours have been over the budget. This is mainly because:
 
  1. The modification of the existing Coalescers piping system was not initially budgeted.
 
  2. More efforts were put on the design in order to meet the clearness requirement of the control panel.
 
  3. The girder and other components near the piping system had to be modeled after interference between the piping and structure components were found.
 
  4. The design of the piping support was much more than originally estimated.
 
  
'''Gas Management System'''
+
CTF C3 Interstage Heat Exchanger Removal
* 35% concept planning has been completed.
+
 
* The 3D model was done based on the concept design.
 
* All pneumatic control valves have been ordered.
 
 
    
 
    
Check on parts ordering. Valves, transducers, venturies
 
 
We had a meeting this morning with Creel, Yang, Saringer, and Thilan. We are working on the schedule for this work as it pertains to dovetailing with operations.
 
 
 
  
JLAB Vaporizer (Perry)
 
  
We have most of the parts. The installation is on hold. It might be used as a filler job if things ever get light. Robert will check if there is any instrumentation and controls associated. Not this year.
+
Install redundant 12V power supplies for cryo cons
  
  
CHL to FEL Utubes (Perry, Corey)
+
'''CHL to FEL Utubes (Perry, Corey)'''
  
  
ESR Summer Maintenance Plan (Schleeper, Radovic, Carlton)
+
'''CHL1 Regeneration Skid Removal (Schleeper, Thompson)'''
  
Change adsorber carbon. Replace CAMAC controls.
 
 
 
 
CHL1 Regeneration Skid Removal (Schleeper, Thompson)
 
 
-Helium line can be isolated and blanked at anytime with LOTO.
 
-Helium line can be isolated and blanked at anytime with LOTO.
-Water lines can be blanked when CHL1 is down and water is isolated.
+
-Water lines isolated.
 
-Vacuum line can be isolated when CHL1 cold box is off line and warm.
 
-Vacuum line can be isolated when CHL1 cold box is off line and warm.
  
 +
 +
Change SC1 and SC2 batteries change
  
  
 
4. JLAB External Group Projects
 
4. JLAB External Group Projects
  
UITF (Perry, Radovic, Carlton)
+
'''UITF (Perry, Radovic, Carlton)'''
  
Thermosiphon being installed. Utubes are being fabricated. The electrical controls work will start after guard vacuum.
+
Thermosiphon installed and pressure test complete. Utubes have been fabricated. Controls need to be finished.
  
  
  
CHL2 Main Compressor Oil Level Alarms (Saringer, Wright)
+
5. JLAB External Lab Projects
  
  
CHL
+
'''LCLS2 (Dixon)'''
  
Inspection of Relief Devices per Pressure System's Requirement: Started CTF and CHL2. Meeting yesterday to decide path forward. Alicia is writing several task hazard analysis, CTList, TOSP. We are running out of time.
+
Recovery compressor skids electrical is being cleaned up
  
 +
Guard Vacuum Skid electrical is about 95% complete
  
5. JLAB External Projects
+
Two water skids are in checking phase
  
 +
Bayonets. Jay is working slightly ahead of schedule.
  
LCLS2 (Dixon)
 
  
We are building two recovery compressors. Due in July 17'. (Issac) We are building a guard vac skid for LCLS2. Not started. Due end of October 17'(Issac). We might also fabricate a water skid. FDR for 2K cold box Mar 9. Issac and Stapleton found grit or metal shavings in the inlet piping of the compressor. Bill Crahen is investigating.
+
6. Summer Maintenance Work Plan (All)
  
We are starting to buy hardware to build 230 bayonets in approximately 6-7 months.
+
PRIORITY
  
Shop is starting to cut metal for the vacuum skid.
+
CHL1 SC1R Piping Modifications (engineering/design $, parts $, labor $$)
  
 +
ESR gas management carbon bed maintenance (engineering/design $, parts $, labor $$)
  
CTF CMTF Junction Box
+
ESR CAMAC to PLC conversion (engineering/design $$$, parts $$$, labor $$$)
  
Repair of EV245RT Coming up with preliminary design for applying force without an EV. Drawings are under review.
+
ESR Relief valve validation (engineering/design $$$, parts $$$, labor $$$)
 
 
 
 
 
 
 
 
 
 
6. Summer Maintenance Work Plan (All)
 
 
 
PRIORITY
 
  
 
CHL1 and CHL2 electrical maintenance including controls
 
CHL1 and CHL2 electrical maintenance including controls
 
GPP CTF gas management skid and Kinney piping move (engineering/design $$, parts $$$, labor $$$)
 
  
 
CHL1 regen skid disconnect (engineering/design 0, parts 0, labor $)
 
CHL1 regen skid disconnect (engineering/design 0, parts 0, labor $)
 
  
 
Add e-stop guards on all systems (engineering/design $, parts $, labor $)
 
Add e-stop guards on all systems (engineering/design $, parts $, labor $)
 
SC1 Vacuum Controls (engineering/design 0, parts 0, labor $)
 
 
CHL1 C3 - Load Valve Readback and Power-meter (engineering/design ?, parts ?, labor ?) - Can be done anytime
 
  
 
CHL1 C6 - Load Valve Readback Calibration (engineering/design 0, parts 0, labor $) - Can be done anytime
 
CHL1 C6 - Load Valve Readback Calibration (engineering/design 0, parts 0, labor $) - Can be done anytime
Line 124: Line 94:
 
CHL2 MCS2 Retighten Flexitalic Gaskets per torque spec. (engineering/design 0, parts 0, labor $)
 
CHL2 MCS2 Retighten Flexitalic Gaskets per torque spec. (engineering/design 0, parts 0, labor $)
  
CHL Hurricane Relief System - EV for SLinac not functional (engineering/design ?, parts ?, labor ?)
+
CHL2 compressor bellows restraint rods
  
  
Line 132: Line 102:
  
 
CHL1 MCB1 Vacuum - Controls and Equipment (engineering/design $, parts $$$, labor $)
 
CHL1 MCB1 Vacuum - Controls and Equipment (engineering/design $, parts $$$, labor $)
 
 
NOT POSSIBLE
 
  
 
CHL2 SC2 cold compressor power feedthru replacement (engineering/design 0, parts 0, labor $$)
 
CHL2 SC2 cold compressor power feedthru replacement (engineering/design 0, parts 0, labor $$)
Line 168: Line 135:
  
  
7. Long Range Plans (Wright, Creel)
+
7. Long Range Plans (Wilson, Creel)
  
 
Jobs we are considering in no particular order
 
Jobs we are considering in no particular order
  
ESR gas management carbon bed maintenance (engineering/design $, parts $, labor $$)
 
  
ESR CAMAC to PLC conversion (engineering/design $$$, parts $$$, labor $$$)
 
  
 
?
 
?
 
Action Items
 
Action Items
 
1.
 
 
2. Before next meeting the persons whose name appears beside an item will write a short update.
 
 
3. Complete summer maintenance list
 
 
4. Need to start thinking about a new 2K cold box design using FRIB/LCLS2 cold compressor designs.
 
 
5. Need to start pushing the engineering/design effort forward for the ESR2 plant.
 
 
 
Action Item Updates
 
  
 
1.
 
1.

Latest revision as of 14:13, 14 November 2017

Attendance

Nusair, Dixon, Thompson, Creel, Radovic, Dixon, Butler, Radovic, Wijeratne, Norton, Laverdure , Schleeper, Yang, Perry,


Goals

The purpose of this weekly meeting is to discuss plant operations and group projects with the cryogenics group managers and supervisors. During this meeting we will discuss ongoing and future projects, priorities, manpower, schedules, expenditures, and problems.


Agenda and Notes

1. Safety


2. Schedule

Plan is to run CHL1 and CHL2 at 2K until mid March.


3. JLAB Internal Group Projects

GPP (Yang, Thilan)

Kinney Pump Relocation


Main Gas and Recovery Gas Management Systems


CTF C3 Interstage Heat Exchanger Removal



Install redundant 12V power supplies for cryo cons


CHL to FEL Utubes (Perry, Corey)


CHL1 Regeneration Skid Removal (Schleeper, Thompson)

-Helium line can be isolated and blanked at anytime with LOTO. -Water lines isolated. -Vacuum line can be isolated when CHL1 cold box is off line and warm.


Change SC1 and SC2 batteries change


4. JLAB External Group Projects

UITF (Perry, Radovic, Carlton)

Thermosiphon installed and pressure test complete. Utubes have been fabricated. Controls need to be finished.


5. JLAB External Lab Projects


LCLS2 (Dixon)

Recovery compressor skids electrical is being cleaned up

Guard Vacuum Skid electrical is about 95% complete

Two water skids are in checking phase

Bayonets. Jay is working slightly ahead of schedule.


6. Summer Maintenance Work Plan (All)

PRIORITY

CHL1 SC1R Piping Modifications (engineering/design $, parts $, labor $$)

ESR gas management carbon bed maintenance (engineering/design $, parts $, labor $$)

ESR CAMAC to PLC conversion (engineering/design $$$, parts $$$, labor $$$)

ESR Relief valve validation (engineering/design $$$, parts $$$, labor $$$)

CHL1 and CHL2 electrical maintenance including controls

CHL1 regen skid disconnect (engineering/design 0, parts 0, labor $)

Add e-stop guards on all systems (engineering/design $, parts $, labor $)

CHL1 C6 - Load Valve Readback Calibration (engineering/design 0, parts 0, labor $) - Can be done anytime

CHL2 MCS2 Retighten Flexitalic Gaskets per torque spec. (engineering/design 0, parts 0, labor $)

CHL2 compressor bellows restraint rods


POSSIBLE

CHL1 MCB CAMAC to PLC conversion (engineering/design $, parts $, labor $$$)

CHL1 MCB1 Vacuum - Controls and Equipment (engineering/design $, parts $$$, labor $)

CHL2 SC2 cold compressor power feedthru replacement (engineering/design 0, parts 0, labor $$)

CHL1 vaporizer cold piping (engineering/design 0, parts 0, labor $$$)

Spare utubes for c50 and c100 (engineering/design 0, parts $$, labor $$)

CHL/FEL shield utube (engineering/design $, parts $, labor $)

CHL Purifier LN2 Solenoid Replacement (engineering/design 0, parts $, labor $) - Can be done anytime

CHL1 MCB1 - MCS1 Rusty Flange, Bolt Change-out (engineering/design 0, parts 0, labor $)

SBR CBX Isolation (engineering/design $, parts $, labor $$??)

SBR C1/C2 - Install Current Transducer (engineering/design ?, parts ?, labor ?)

SBR C1 - Loading itself (engineering/design ?, parts ?, labor ?) - Can be done anytime

ESR-TL (EV11139) Valve Re-build (engineering/design 0, parts $, labor $)

CHL Recovery 10DR Valve - dismantle, header inspection (engineering/design 0, parts $/2, labor $)

CHL2 SCW Solenoid with Spools ((engineering/design $, parts $, labor $) - SV Ordered Already

CHL2 GN2 Vent Piping (engineering/design 0, parts 0, labor $)

CHL2 UCBX/LCBX backup vacuum - connect to K100 vacuum skid (engineering/design $, parts $, labor $)

CHL2 MCS2 - Replace valve on Purifier Discharge Header (engineering/design $, parts $, labor $) - Valve already bought.


7. Long Range Plans (Wilson, Creel)

Jobs we are considering in no particular order


? Action Items

1.