Difference between revisions of "Meeting Feb 06, 2016"

From Cryowiki
Jump to navigationJump to search
(Created page with " == Attendance == Creel, Scanlon, Oren, Dixon, Bevins, Arenius == Agenda and Notes == '''1. Manpower ''' Rotendra starts in two weeks. He will start on LCLS2. New LCLS...")
 
 
Line 10: Line 10:
 
'''1. Manpower '''
 
'''1. Manpower '''
  
Rotendra starts in two weeks. He will start on LCLS2.
+
Rotendra starts in one week. He will start on LCLS2.
  
 
New LCLS2 manpower plan anticipated by Monday next week so we can plan.
 
New LCLS2 manpower plan anticipated by Monday next week so we can plan.
Line 17: Line 17:
 
'''2. Project '''
 
'''2. Project '''
  
The 2K cold box review is complete. Mike will work with Hung Yu and Nate to set an FDR for the cold box.
+
The 2K FDR is scheduled 9 Mar at JLAB.
  
LN2 Dewars have been awarded.  
+
Controls design workshop is at SLAC 8 Feb. Scanlon says requirements keep changing. It was a procurement readiness review but now they are asking for ICD's FRS's etc. Post review should allow Chris to release gas management and utility ($500K) and then the 4K and 2K cold boxes ($500K) (paperwork is at 80% complete).  
  
Oil removal vessels awarded to Eden.
+
Ancillary equipment specs at SLAC for signatures (MCC, generator, UPS)
 
 
Controls design review moved to Feb 17'. Scanlon says requirements keep changing. It was a procurement readiness review but now they are asking for ICD's FRS's etc.
 
 
 
Issues at the Directors Review were resolved.
 
 
 
Ancillary equipment specs at SLAC for signatures.
 
  
 
Internal 2K piping is being worked with Hung yu and Damon Rath.
 
Internal 2K piping is being worked with Hung yu and Damon Rath.
  
Smith groups review of the installation package is complete. They came up with a number of recommendations.  
+
Smith groups review of the installation package is complete. They came up with a number of recommendations. Dana needs help identifying locations of field mounted devices.  
  
  
 
'''3. Recovery Compressor Progress '''
 
'''3. Recovery Compressor Progress '''
 +
 +
Assembling frames and piping components.
  
  
Line 41: Line 37:
 
There is more potential fabrication work for a turbine and cold compressor water skid.
 
There is more potential fabrication work for a turbine and cold compressor water skid.
  
 
+
Fabrication bayonets
  
 
== Action Items ==
 
== Action Items ==

Latest revision as of 14:37, 6 February 2017


Attendance

Creel, Scanlon, Oren, Dixon, Bevins, Arenius


Agenda and Notes

1. Manpower

Rotendra starts in one week. He will start on LCLS2.

New LCLS2 manpower plan anticipated by Monday next week so we can plan.


2. Project

The 2K FDR is scheduled 9 Mar at JLAB.

Controls design workshop is at SLAC 8 Feb. Scanlon says requirements keep changing. It was a procurement readiness review but now they are asking for ICD's FRS's etc. Post review should allow Chris to release gas management and utility ($500K) and then the 4K and 2K cold boxes ($500K) (paperwork is at 80% complete).

Ancillary equipment specs at SLAC for signatures (MCC, generator, UPS)

Internal 2K piping is being worked with Hung yu and Damon Rath.

Smith groups review of the installation package is complete. They came up with a number of recommendations. Dana needs help identifying locations of field mounted devices.


3. Recovery Compressor Progress

Assembling frames and piping components.


4. Additional work

There is more potential fabrication work for a turbine and cold compressor water skid.

Fabrication bayonets

Action Items

1. Dana is kicking in money to add a PC and overhead monitor to the small conference room.

2.