Difference between revisions of "Meeting Feb 06, 2016"
(Created page with " == Attendance == Creel, Scanlon, Oren, Dixon, Bevins, Arenius == Agenda and Notes == '''1. Manpower ''' Rotendra starts in two weeks. He will start on LCLS2. New LCLS...") |
|||
Line 10: | Line 10: | ||
'''1. Manpower ''' | '''1. Manpower ''' | ||
− | Rotendra starts in | + | Rotendra starts in one week. He will start on LCLS2. |
New LCLS2 manpower plan anticipated by Monday next week so we can plan. | New LCLS2 manpower plan anticipated by Monday next week so we can plan. | ||
Line 17: | Line 17: | ||
'''2. Project ''' | '''2. Project ''' | ||
− | The 2K | + | The 2K FDR is scheduled 9 Mar at JLAB. |
− | + | Controls design workshop is at SLAC 8 Feb. Scanlon says requirements keep changing. It was a procurement readiness review but now they are asking for ICD's FRS's etc. Post review should allow Chris to release gas management and utility ($500K) and then the 4K and 2K cold boxes ($500K) (paperwork is at 80% complete). | |
− | + | Ancillary equipment specs at SLAC for signatures (MCC, generator, UPS) | |
− | |||
− | |||
− | |||
− | |||
− | |||
− | Ancillary equipment specs at SLAC for signatures | ||
Internal 2K piping is being worked with Hung yu and Damon Rath. | Internal 2K piping is being worked with Hung yu and Damon Rath. | ||
− | Smith groups review of the installation package is complete. They came up with a number of recommendations. | + | Smith groups review of the installation package is complete. They came up with a number of recommendations. Dana needs help identifying locations of field mounted devices. |
'''3. Recovery Compressor Progress ''' | '''3. Recovery Compressor Progress ''' | ||
+ | |||
+ | Assembling frames and piping components. | ||
Line 41: | Line 37: | ||
There is more potential fabrication work for a turbine and cold compressor water skid. | There is more potential fabrication work for a turbine and cold compressor water skid. | ||
− | + | Fabrication bayonets | |
== Action Items == | == Action Items == |
Latest revision as of 14:37, 6 February 2017
Attendance
Creel, Scanlon, Oren, Dixon, Bevins, Arenius
Agenda and Notes
1. Manpower
Rotendra starts in one week. He will start on LCLS2.
New LCLS2 manpower plan anticipated by Monday next week so we can plan.
2. Project
The 2K FDR is scheduled 9 Mar at JLAB.
Controls design workshop is at SLAC 8 Feb. Scanlon says requirements keep changing. It was a procurement readiness review but now they are asking for ICD's FRS's etc. Post review should allow Chris to release gas management and utility ($500K) and then the 4K and 2K cold boxes ($500K) (paperwork is at 80% complete).
Ancillary equipment specs at SLAC for signatures (MCC, generator, UPS)
Internal 2K piping is being worked with Hung yu and Damon Rath.
Smith groups review of the installation package is complete. They came up with a number of recommendations. Dana needs help identifying locations of field mounted devices.
3. Recovery Compressor Progress
Assembling frames and piping components.
4. Additional work
There is more potential fabrication work for a turbine and cold compressor water skid.
Fabrication bayonets
Action Items
1. Dana is kicking in money to add a PC and overhead monitor to the small conference room.
2.