11/17/2016 Meeting
Attendance
Thompson, Creel, Dixon, Wright, Oren, Michalski, Arenius
Agenda and Notes
1. Operations
LINAC
Magnet power supply repaired.
2L06 windows were repaired. Utubes were reinstalled in 2L06 and 2L07 and they were recooled and a pumpdown was completed.
CHL1
Techs continue working on connecting new CHL C8
CHL2
Normal
ESR
ESR cold box shutdown this week due to a CAMAC problem. It was also noticed that T2 did not stop rotating when its inlet valve closed during the shutdown. We are suspecting contamination on the inlet valve. We are making a plan to shutdown and warm up the circuit. The plan will be scheduled with ops or executed if the plant shuts down again.
Hall C SHMS Q2 cooldown planned for Monday.
CTF
Normal.
HDR
Normal.
2. Projects
UITF
Warm return VJ line section above cryomodule was installed and work is moving forward on 1/4CM installation.
MSU
LCLS2
Installation work for the cryo plant was officially moved to the SLAC team. The team is currently evaluating the bids on some of the utility support equipment. Bayonets etc. are complete and we are going to ship them to PHPK as soon as possible. Dana will advise when paperwork is done. The recovery compressor parts purchasing is underway. Work has begun on the frames.
LCLS2 safety people visited this week asking questions on safety related items such as ODH, pressure systems, and readiness reviews.
3. Manpower
The new EE regular employee and ECAD contract employee started on Nov 1. He is currently working on both LCLS2 and UIM.
4. Info from Will
1. Watch spending on OPS and ENG accounts. Try to keep spending to critical "stop work" items.
4. Other
Action Items
1. Must keep meeting to no more than 30 minutes