Meeting Oct 31, 2016

From Cryowiki
Revision as of 14:08, 31 October 2016 by Creel (talk | contribs) (Created page with "== Attendance == Creel, Dixon, Arenius, Bevins, Scanlon, Oren == Agenda and Notes == '''1. Manpower ''' JLAB management held up contractor extensions and some personnel...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigationJump to search

Attendance

Creel, Dixon, Arenius, Bevins, Scanlon, Oren


Agenda and Notes

1. Manpower

JLAB management held up contractor extensions and some personnel have been sent home until its worked out. Will has a meeting with Mont and Allison this afternoon at 3pm to work out the issues. JLAB management wants to know if we can move staff designers off of other things on to the jobs being worked by the contractors.

The EE will be here Nov 1. This person to be used to support LCLS2, UIM OPs.

The ECAD contract designer started 31 Oct


2. Recovery Compressor and Guard Vacuum Skid Fabrication

Cryo did provide capital and manpower estimates to LCLS2. We have started working on the skids. Compressor bodies have not been signed off. The June delivery date will likely move accordingly.


3. 2K Cold Box Step File

Mike Bevins has passed on a request from Preble for a copy of the latest STEP file. We did not see a problem as long as it was tagged as JLAB intellectual property.

Action Items

1.

2. Cryo to complete an estimate for fabricating two recovery compressors by Friday. (DONE)