General EEEMCal Meeting Summary 10/8/21
Jump to navigation
Jump to search
PARTICIPANTS: A. Bazilevsky, C. Munoz, H. Mkrtchyan, H. Marukyan, N. Santiesteban, R. Fatemi, T. Horn, L. Guo, V. Tadevosyan, D. Hasell, V. Berdnikov, Crytur-USA, Crytur-CZ
PROPOSALS
- Document writing ongoing for all proto-collaborations
- ATHENA - main contact: Vladimir
- CORE - main contact: Carlos
- ECCE - main contact: Tanja
- Action: circulate any drafts as they are and/or post on Wiki for EEEMCAl team to review and comment
SIMULATIONS
ECCE (Nathaly)
- Discussion of EEEMCAL and barrel calorimeter neutral pion mass resolutions
- Approach: look at reconstructed pion mass for calorimeter and examine resolution of mass with changing energy
- observe that width of mass decreases with increasing energy - makes sense as one gets a mesh or merged events (cannot distinguish photons anymore)
- Probability of meshing in barrel near 100% at and above 10 GeV - so cannot distinguish two photons with this setup
- note that calorimeter location has an inner radius of ~80cm - too close for present 4cmx4cm granularity
- solution: use finer granularity, e.g., 3cm x 3cm
- question: why does the probability for merging not go to zero? - possible explanation is that an energy cut is implemented, e.g., events where second photon at very low energy would not be included
ATHENA (AANL team)
- working on extracting EEEMCAL information from the simulation
EEEMCAL DESIGN
- Work ongoing on additional support for SciGlass since blocks are longer than crystals
- use internal ring to provide additional support for glass
- Inner ring - stainless steel - working on implementing cooling from inside taking into account all space constraints
- Also working on implementation of readout - 16 SiPM on each module
- Major next steps awaiting decision on detector
- Action: think in which places to publish the design information
- EEEMCAL internal - for sure
- E&D EIC Project - is there a specific place for that?
- Other
PROTOTYPES
JLAB SCIGLASS AND SiPM 25um READOUT/SRO TESTS
- Readout and SRO detector prototypes installed in Hall D this week
- Many SciGlass blocks were received damaged and awaiting replacement for 3x3 test - currently have 3 blocks installed in a beam test bench setup
- Plan for prototypes and SciGlass
- start taking data with PWO SiPM readout and SRO test
- take data on SciGlass individual blocks in test bench
- next: once replacements arrive install 3x3 SciGlass prototype and take data
- Change in prototype beam time schedule
- December beam time originally planned for tests of 40cm SciGlass was cancelled --> test of 3x3 prototype with long modules will be in 2022 earliest
- Energy range of prototype beam tests - energy resolution provided by pair spectrometer and is on level of 0.6%
- 3x3 prototypes have one energy only (~5 GeV) at this time. In future hope to install instrumentation that allows for remotely accessing a range between 2.5 - 6 GeV
- 12x1 test bench can access a range
- Plan for Testing SciGlass
- take data with prototype - modules are 20cm long, so leakage is expected
- compare to simulation
JLAB CRYTUR PROTOTYPE
- Assembly and testing is ongoing at Crytur/CZ
- For pretest at JLab before beam:
- plan to take data with cosmic muons (1Hz) and/or sources to test channels
- Action: send list of items that are needed for pretest and any additional material needed for beam test
DESY
- Preparations ongoing - instrumentation has been shipped to DESY
NEXT MEETING: 29 OCTOBER AT 8:30AM ET